Laserfiche WebLink
Last unit cost update: 7/1/2007 Page 5 of 6 <br /> %LIAB. TOTAL <br />STRUCTURE or ITEM DESCRIPTION QUANTITY UNIT CIRCES DEMOLITION MENU SELECTION UNIT COST #VALUE! (ACTUAL) <br />ft ft ft If in <br />Water tank <br />Superstructure 28 86 162,637 CF Demo/disp./exc. pit- 10K' haul $0.22 $35,454.77 100% $35,454.77 <br />Steel ring for foundation 1 86 270 CF Demo/disp./exc. pit - 10K' haul $0.22 $58.89 100% $58.89 <br />Shower trailer 12 40 10 4,600 CF Demo/disp./exc. pit - 10K' haul $0.22 $1,046.40 ' <br />Shower trailer 12 40 10 4,800 CF Demo/disp./exc. pit- 10K' haul $0.22 $1,046.40 100% $1,046.40 <br />Materials storage building <br />Superstructure 130 30 17 64,350 CF Demo/disp./exc. pit - 10K' haul $0.22 $14,028.30 100% $14,028.30 <br />Floor 130 30 8 3,900 SF Demo.disp exc. pit, 8" th. - 200 ft. $2.6800 $10,452.00 100% $10,452.00 <br />Footings 2 3 266 266 LF Demo/disp./exc. pit, 2'X3- 200 ft. $24.0800 $6,405.28 100% $6,405.28 <br />Apron 130 10 8 1,300 SF Demo.disp exc. pit, 8" th. - 200 ft. $2.6800 $3,464.00 100% $3,484.00 <br />Office/bathhouse parking lot expansion 1460 1,460 SY Bitum. pave., demo. only, 4-6" th. $5.2500 $7,665.00 100% $7,665.00 <br />Light poles at bathhouse 4 40 40 LF Power/telephone line, wood - Double or H po $5.1100 $204.40 100% $204.40 <br />Warehouse <br />Superstructure 33 30 11 10,890 CF Demo/disp./exc. pit- 10K' haul $0.22 $2,374.02 100% $2,374.02 <br />Floor 33 30 8 990 SF Demo.disp exc. pit, 8" th. - 200 ft. $2.68 $2,653.20 100% $2,653.20 <br />Footer 2 3 126 126 LF Demo/disp./exc. pit, 2'X3'- 200 ft. $24.08 $3,034.06 100% $3,034.08 <br />Wall 5 6 126 126 SF Demo.disp exc. pit, 6" th. - 200 ft. $2.21 $278.46 100% $278.46 <br />Concrete barriers for benches and roads (120) 10 2 120 120 EA Railing, roadside guiderail posts only $10.46 $1,255.20 100% $1,255.20 <br />TLO conveyor/pulley <br />Enclosures 23 54 17 21,114 CF Demo/disp./exc. pit- 1OK' haul $0.22 $4,602.85 100% $4,602.65 <br />Floor site 1 23 54 1,242 SF Demo.disp exc. pit, 8" th. - 200 ft. $2.68 $3,328.56 100% $3,328.56 <br />Floor site 2 18 6 108 SF Demo.disp exc. pit, 8" th. - 200 ft. $2.68 $289.44 100% $289.44 <br />Site 1 headhouse extension 8,044 CF Demo/disp./exc. pit- 10K' haul $0.22 $1,753.59 100% $1,753.59 <br />Site 2 headhouse extension 34 15 15 7,650 CF Demo/disp./exc. pit- 10K' haul $0.22 $1,667.70 100% $1,667.70 <br />Guardrails at mine entrance and RIDE road 750 750 LF Railing, roadside guiderail and posts $9.38 $7,035.00 100% $7,035.00 <br />Mine entrance gate 1 4 30 30 30 LF Fencing, chain link - to 6 ft. high $1.92 $57.60 100% $57.60 <br />Mine entrance gate 2 4 30 30 30 LF Fencing, chain link - to 6 ft. high $1.92 $57.60 100% $57.60 <br />Fence at NSS (3-strand) 2,100 2,100 LF Fencing, barbed wire - 3 strand $1.07 $2,247.00 100% $2,247.00 <br />Remove additional entrance road pavement 1936 1,936 SY Bilum. pave., demo. only, 3" th. $3.20 $6,195.20 100% $6,195.20 <br />Dozer service facility <br />Superstructure 30 42.6 50 63,900 CF Demo/disp./exc. pit - 10K' haul $0.22 $13,930.20 100% $13,930.20 <br />Floor 42.6 50 6 2,130 SF Demo.disp exc. pit, 6" th. - 200 ft. $2.01 $4,281.30 100% $4,281.30 <br />Footings 2 3 73 73 LF Demo/disp./exc. pit, 2'X3'-200 ft. $24.08 $1,757.84 100% $1,757.84 <br />Retaining walls 8 25 200 SF Demo.disp exc. pit, 12" th. - 200 ft. $4.41 $862.00 100% $882.00 <br />Retaining walls 12 72 864 SF Demo.disp exc. pit, 12" th. - 200 ft. $4.41 $3,810.24 100% $3,810.24 <br />Apron 6 12 24 4 CY Concr. pave., demo., 7-24" th., reinf. $92.00 $327.11 100% $327.11 <br />Apron 8 17 24 5 CY Concr. pave., demo., 7-24" th., reinf. $92.00 $463.41 100% $463.41 <br />Materials Storage Bench <br />Ditches 1,626 1,626 SF Demo.disp exc. pit, 8" th. - 200 ft. $2.68 $4,357.66 100% $4,357.68 <br />Surface area asphalt 14520 14,520 SY Bitum. pave., demo. only, 4-6" th. $5.25 $76,230.00 100% $76,230.00 <br />Building walls 320 1 320 SF Demo.disp exc. pit, 10" th. - 200 ft. $3.68 $1,177.60 100% $1,177.60 <br />Locker room addition <br />Superstructure 10 61 51,240 CF Demo/disp./exc. pit- 10K haul $0.22 $11,170.32 100% $11,170.32 <br />Floor 10 4 840 SF Demo.disp exc. pit, 4" th. - 200 ft. $ 1.34 $1,125.60 100% $1,125.60 <br />Footings 84 1 188 186 LF Demo/disp./exc. pit, 1'X2'-200 ft. $8.03 $1,509.64 100% $1,509.64 <br />Curb 84 188 188 LF Concr. curbing, demo. only, no reinfor. $2.78 $522.64 100% $522.64 <br /> 1 <br />Remove DMEA powerlines 350 350 LF Power/telephone line, wood - Double or H po $5.11 $1,788.50 100% $1,788.50 <br />Ventilation facility intake shaft <br />Collar 15 34 SF Demo.disp axis. pit, 12" th. - 50 ft. $3.88 $131.92 100% $131.92 <br />Collar base/footer 40 4 34 SF Demo.disp axis. pit, 12" th. - 50 ft. $3.88 $131.92 100% $131.92 <br />Exhaust shaft collar 34 12 34 SF Demo.disp exis. pit, 12" th. - 50 ft. $3.88 $131.92 100% $131.92 <br />Base/footer 43 42 4 212 CY Concr. pave., demo., 7-24" th., reinf. $92.00 $19,504.00 100% $19,504.00 <br />Main fans/motor houses 28 10 4 12 CY Concr. pave., demo., 7-24" th., reinf. $92.00 $1,104.00 100% $1,104.00 <br />Main fans/motor houses 34 10 4 12 CY Concr. pave., demo., 7-24" th., reinf. $92.00 $1,104.00 100% $1,104.00 <br />Fan ducting 8 10 560 22,400 CF Demo/disp./exc. pit - 10K' haul $0.22 $4,883.20 100% $4,883.20 <br />Culverts (from Table 44E): <br />30 C1-1 30 30 LF Pipe, CMP - 30 in. diam. $4.42 $132.60 100% $132.60 <br />18 C1-1A 40 40 LF Pipe, CMP - 18 in. diam. $2.35 $94.00 100% $94.00 <br />30 C1-1D 25 25 LF Pipe, CMP-30 in.diam. $4.42 $110.50 100% $110.50 <br />24 C1-1E 30 30 LF Pipe, CMP-24 in.diam. $3.15 $94.50 100% $94.50 <br />21 C1-2 480 480 LF Pipe, CMP-21 in. clam. $2.93 $1,406.40 100% $1,406.40 <br />21 C1-2A 280 280 LF Pipe, CMP-21 in.diam. $2.93 $820.40 100% $820.40 <br />18 C1-213 30 30 LF Pipe, CMP - 18 in. diam. $2.35 $70.50 100% $70.50 <br />18 C1-3 190 190 LF Pipe, CMP - 18 in. diam. $2.35 $446.50 100% $446.50 <br />36 C1-4 360 360 LF Pipe, CMP - 36 in. diam. $4.86 $1,749.60 100% $1,749.60 <br />2-3.5'x5.3'' C1-5A 135 135 LF Pipe, RCP - 42 in. diam. $13.52 $1,825.20 100% $1,825.20 <br />42 C1-58 260 260 LF Pipe, CMP-48 in.diam. $6.19 $1,609.40 100% $1,609.40 <br />42 C1-5C 30 30 LF Pipe, CMP-48 in. clam. $6.19 $185.70 100% $185.70 <br />18"/2.8'x4' a C1-6 230 230 LF Pipe, RCP - 18 in. diam. $3.28 $754.40 100% $754.40 <br /> Total for this page before location adjustment $275,253.29 <br /> Location adjustment: 0.92 Total for this page after location adjustment $254,113.84