Laserfiche WebLink
BOREHOLE SEALING WORK <br />Task #: 69b <br />Mine: Foidel Creek Mine Date: 9/2/09 <br />Permit no.: C1982-056 User: JHB <br />Permitting action: TR69 <br /> Cwt of bulk cement Water <br />2,500 gal <br />Octoplug Cut surface <br /> <br />Hole <br />Total <br />Hole (assuming 94 Ibs of <br />Cement cost <br />t <br />1 <br />18 <br />f <br />f <br />C Total rig <br /> <br />Ri <br />i <br />Ri <br />i <br />i Rig wl crew <br /> <br />h <br />l <br />T <br />l truck wl <br />water truck <br />d <br />i <br />(Circes, <br />casing 8 <br />Hole diam. depth volume cemen <br />per <br />. <br />ement <br />c <br />o <br />per cwt g setup t <br />me <br />g t <br />me to t <br />me our <br />y rate <br />ota r <br />ver cost <br />wldriver $19.57 mark Total cost <br /> <br />(in) <br />(ft) <br />(cf) hole, that is 100 Ibs total cost <br />(CIRCES) per hole (hr) fill hole (setup + (Circes, Reed rig cost (rig fill <br />hourly rate <br />per in. <br />(Circes, <br /> of cement fills 1.25 fill) drill, 9.0") (Circes) <br />a diam.) $10.9011f) <br /> truck rate) r <br />te) <br />6rt underflow, 8 540 189 150.0 $6.90 $1,035 1.45 1.89 3.34 $219.67 $733 $51 $96 $157 $23 $2,043 <br />Total hours 3.34 <br />Divided by number of rigs 1 <br />Net total hours 3.34 <br />Grand total <br />.y'ri