Laserfiche WebLink
nominal 3-4 yard hoisting bucket. The shaft cuttings were placed by awheel-loader in a 14-foot deep, lined <br />temporary mine development waste pit excavated within the shaft pad, adjacent to the shaft excavation, as shown <br />on Maps EX16E-M1 and M2. The cuttings pit is lined with a nomina130-mil PVC flexible membrane liner having <br />a permeability of ~10-12 cm/sec. The PVC liner is covered with approximately 6-8 inches of pit-run material to <br />protect the liner. The shaft concrete lining was placed in nomina120- to 30-foot lifts in cycle with the drilling and <br />mucking operation, using acurb-ring and slip-form assembly. During excavation, the shaft work area was <br />ventilated using ventilation ducting and a permissible surface fan. Once the blind sink excavation reached the coal <br />seam, the work stage was removed and disassembled. <br />The cuttings volume generated by shaft sinking operations is approximately 15,126 cubic yards (22,690 cubic yards <br />when swelled by 50 percent, based on 20-foot diameter and 1,300-foot depth). If drainage of water from the <br />excavated material resulted in any significant accumulation of water in the cuttings pit, the water was pumped to a <br />water tanker to maintain essentially dry conditions in the pit. Upon completion of the shaft excavation and concrete <br />liner installation, any minor water accumulation in the cuttings pit were allowed to dry-out, and the collection pit <br />and cutting materials were then be covered with previously placed materials from the shaft collar excavation, <br />graded, and revegetated with a temporary cover. A sign(s) was posted designating the temporary mine <br />development waste pit. The cuttings and shaft collar excavation materials will be utilized to re-fill the shaft during <br />eventual reclamation of the facility. <br />The cement liner serves to isolate the Twentymile Sandstone from the Wadge Overburden. As noted above, apre- <br />grout program is not required in a conventional blind sink. A probe-hole is typically carried down the hole as the <br />shaft is excavated. Water is grouted off from within the excavated shaft as it is encountered. This further assures <br />that, after final closure, the water in this unit is confined and will not seep down on the inside of the shaft. <br />Following completion of shaft excavation and cement lining operations, and removal of equipment from the site, an <br />emergency escape hoist will be installed in the shaft. Hoist installation will involve completion of the following <br />activities, as illustrated by the design information provided in Exhibit 49N, 6MN Emergency Escape Hoist Design <br />Drawings: <br />• Erection of apre-fabricated steel hoist-frame and bull-wheel, approximately 10 x 22 x 25 feet high over the <br />existing 6MN Ventilation Shaft, tying into the existing concrete shaft collar <br />• Fabrication of a steel frame and expanded metal shaft landing and access stairs, tying into the hoist-frame <br />• Fabrication of a similar shaft landing at the bottom of the shaft <br />• Installation in the shaft of guide-ropes for the hoist cage <br />• Excavation for the hoist-house foundation <br />• Forming and pouring of the 20 x 30 foot reinforced concrete hoist-house foundation <br />• Installation of the hoist motor, winch, and associated control equipment on the hoist-house foundation <br />• Erection of the pre-fabricated steel hoist house <br />• Stringing of hoist cable and placement and connection of the 3 x 5 x 8 foot high pre-fabricated hoist cage <br />• Electrical connections (from existing power distribution line) and testing of hoist <br />• Installation of appropriate equipment guards and fencing <br />Underground Utilities Project Components -Concurrent with road construction, a 69-KV power distribution line <br />was extended from the existing substation at the Northwest Mains fan location to apad-mounted transformer at the <br />6 North Mains shaft site. The power distribution line is approximately 3,130 feet long with a total of approximately <br />14 powerpoles and is located adjacent to the proposed access road and within the 50-foot road corridor from road <br />centerline. <br />In conjunction with the 6-North Mains shaft project and extension of the power distribution line, TCC also <br />proposes to construct on the shaft pad a high voltage substation with three power borehole drops, a compressed air <br />station with borehole drop, a rockdust tank station with borehole drop, a bulk material borehole drop and a water <br />borehole drop for the continued development and mining of the Northern and Western Mine Districts. The <br />boreholes were drilled to a nominal 13-inch diameter. Water for drilling operations was either trucked-in by tanker <br />or drawn from Fish Creek using a portable pump (under TCC's Boettler Ditch water right -144 cfs). The cuttings <br />TR09-66 2.05 - 45.6d 02/17/09 <br />