CIRCES Cost EstimatinaSoftware
<br />DEMOLITION WORK
<br />STRUCTURE or ITEM DESCRIPTION DIMENSIONS DEMOLITION MENU SELECTION QUANTITY UNIT UNIT COST TOTAL COST
<br />-Truck Dump Hopper 6600 Demo.ldisp.lappr dump - to 5 mi. 6,600.00 CF $1.0437 $6,888.49
<br />-concrete floor 18" th. x 495 sq.ft. Demo.ldisp. exs. pit, 4" th.- 50 ft. 495.00 SF $1.1173 $553.08
<br />-foundation walls 30" 7963 Demo./disp. exs. pit, 1.5x2'- 50 ft. 7,963.00 LF $10.0559 $80,075.33
<br />
<br />-Reclaim Tunnel 36" belt vibrator 12 Demo./disp. exs. pit, 1.5x3'- 50 R. 12.00 LF $15.0839 $181.01
<br />
<br />-Dump Hopper Conveyor Tunnel 10' dia. x 115 R. Rat wall, steel - 12.1' D x 20' H 115.00 LF $50.0000 $5,750.00
<br />
<br />-dump Hopper Conveyor 147 Lin. Ft. Conveyor, elevated - 8' Wx 10'H 147.00 LF $45.3900 $6,672.33
<br />
<br />-Crusher building 20160 cubic feet Demo.ldisp.lappr. dump - to 5 mi. 20,160.00 CF $1.0437 $21,041.20
<br />crusher floor 12" th. 672 sq. ft. Demo./disp. exs. pit, 12" th.-200 ft. 672.00 SF $3.3890 $2,277.39
<br />
<br />-Powerhouse (2) 2240 cubic feet Demo.ldisp.lappr. dump - to 5 mi. 2,240.00 CF $1.0437 $2,337.91
<br />-powerhouse floors 224 sq. ft. Demo.ldisp. exs. pit, 8"th.- 200 ft. 224.00 SF $2.2593 $506.09
<br />
<br />-Dust Suppression Pressure Tank Building 1344 Cubic Feet Demo.ldisp.lappr. dump - to 5 mi. 1,344.00 CF $1.0437 $1,402.75
<br />-floor of Dust suppression building 192 sq, ft. X8" th. Demo.ldisp. exs. pit, 8" th.- 200 ft. 192.00 SF $2.2593 $433.79
<br />
<br />-Dust suppression System building 672 cubic feet Demo.ldisp.lappr dump - to 5 mi. 672.00 CF $1.0437 $701.37
<br />-floor of dust suppression system building 96 Demo.1disp. exs. pit, 8"th.- 200 ft. 96.00 SF $2.2593 $216.89
<br />
<br />-Water Storage Tank 6872 Demo.ldisp.lappr. dump - to 5 mi. 6,872.00 CF $1.0437 $7,172.38
<br />
<br />-Railroad track (loop & Spur) 17424 Lin. Feet Railroad track - Ties and track 17,424.00 LF $7.5400 $131,376.96
<br />ballast included in Task 1
<br />-Loadout building 63700 cu. ft. Demo.ldisp.lappr dump - to 5 mi. 63,700.00 CF $1.0437 $66,484.33
<br />-footings of Loadout building 130 fin. ft. Demo.ldisp. exs. pit, 2x3'- 200 ft. 130.00 LF $20.3338 $2,643.39
<br />
<br />-Loadout Belt (60" W) 290 Lin. Ft. Conveyor, overland - 5'W x 6'H 290.00 LF $15.1400 $4,390.60
<br />
<br />-Raft Car positioner & hopper 82560 Demo.ldisp.lappr dump - to 5 mi. 82,560.00 CF $1.0437 $86,168.71
<br />-positioner & hpper walls 12" th. X 584 sq. ft. Demo.ldisp. exs. pit, 12"th.-200 ft. 584.00 SF $3.3890 $1,979.16
<br />
<br />
<br />-Rail Car Dump Hopper Reclaim Tunnel- Belt 60" W x 1208. L Conveyor, overland - 5'W x 6'H 120.00 LF $15.1400 $1,816.60
<br />-floor 12'th.X3360s.f. Demo.1disp. exs. pit, 12"th.-10K ft. 3,360.00 SF $3.4143 $11,471.91
<br />-24" foundation walls 24" th. X 5248 s.f. Demo./disp. exs. pit, 12" th.-10K ft. 10,496.00 SF $3.7538 $39,399.79
<br />
<br />-Dump Hopper Belt conveyor Tunnel 16 dia. 106 Lin. Ft. remove converyor tunnel 106.00 LF $240.9000 $25,535.40
<br />
<br />-belt-60"w. 60"W X 146'1 Conveyor, overland - 5'W x 6'H 146.00 LF $15.1400 $2,210.44
<br />
<br />
<br />-Radial stacker pad 12"th.X3625 s. f. Demo.ldisp. exs. pit, 4"th.- 50 ft. 3,625.00 SF $1.1173 $4,050.30
<br />-Radial stacker boom 1401. f. Conveyor, elevated- 5' W x 6'H 140.00 LF $37.8300 $5,296-20
<br />
<br />-Foglet system control building 1920 s.f. Demo.ldisp.lappr. dump - to 5 mi. 1,920.00 CF $1.0437 $2,003.92
<br />
<br />-2 office trailers 19500 cf + 7200 cf Demo.ldisp.lexcav. pit - 10K' haul 26, 700.00 CF $0.2132 $5,692.06
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />JOB COST Subtotal (unadjusted): $526,730 Total Cost (adjusted for location): $486,277
|