My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2009-01-14_REPORT - C1981019
DRMS
>
Day Forward
>
Report
>
Coal
>
C1981019
>
2009-01-14_REPORT - C1981019
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 3:42:52 PM
Creation date
1/15/2009 10:17:51 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
C1981019
IBM Index Class Name
REPORT
Doc Date
1/14/2009
Doc Name
4th Quarter Fill Monitoring
From
Colowyo Coal Company
To
DRMS
Permit Index Doc Type
Waste Pile/Fill Report
Email Name
JRS
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
9
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
East Taylor Fill Inspection Certification <br />On December 8, 2008 and December 31, 2008, 1 inspected the area in which the East Taylor <br />Excess Spoil Fill is being constructed. The purpose of this inspection was to observe status of <br />the underdrain trench construction and subsequent fill placement. This inspection is <br />necessary to satisfy the requirements of CDMG Rule 4.09. 10 (1a) and Rule 4.09.1 (1b). <br />All topsoil stripping within the footprint of the B-B' and C-C' underdrain areas was completed <br />prior to this quarter. No construction progress occurred during the previous quarter. <br />C-C' Underdrain Area: During the first quarter of 2008 (week of January 28, 2008), the C-C' <br />underdrain trench and a lateral drain were excavated by dozer. Moisture resulting from the <br />spring snowmelt subsequently resulted in localized slumping which necessitated re- <br />excavation of the entire underdrain trench and lateral drain prior to rock placement. In July, <br />2008, excavation of the C-C' trench was restarted and subsequently completed. Construction <br />of the trench, along with rock placement, was being performed by the mine's road crew. <br />Fabric placement was being done by Anson Excavation. As of the date of this report, all of <br />the rock placement is completed, and all of the trench has been covered with fabric. <br />B-B' Underdrain Area: Construction of the B-B' underdrain was being performed by Anson <br />Excavation. Trench excavation, rock placement, and fabric placement was started in the Third <br />Quarter. As of the date of this report, all of the rock placement is completed, and all of the <br />trench has been covered with fabric. No excavation or other work below the confluence with <br />the A-A' trench is taking place as of the date of this report. <br />Fill placement within portions of the spoil pile footprint is in progress. This includes lower, mid <br />and upper portions of the C-C' underdrain as well. The A -A! underdrain has not been started. <br />Design requirements for the spoil pile are addressed in Volume 13, Exhibit 21, Item 1, <br />Introductory Letter. Inspection requirements during construction are further detailed in <br />Volume 12, Section 4.09. <br />1 am a Registered Professional Engineer in the State of Colorado and a representative of <br />Environmental Solutions, Inc, P. O. Box 2996, Cheyenne, Wyoming. Being familiar with the <br />Colowyo operation and the coal program permitting process in Colorado, the construction <br />activities related to the East Taylor Fill are in conformance, to the best of my knowledge and <br />experience, as speed in the Introductory pages and the associated report found in Volume <br />13, Exhibit 21, Item 1 and other applicable requirements of the approved permit documents, a <br />portion of CDMG Permit C-81-019. -2922226- <br />#v 0 L /CF 51, <br />Cj 19 <br />32257 ;-A <br />i..S?ONAL E?G <br />THOMAS C PETERSON <br />P.E. No. 32257 <br />i /? z I o,9 <br />DATE
The URL can be used to link to this page
Your browser does not support the video tag.