Truck/Loader Team Work cont'd Task #: 09b sheet 2 of 2 <br />Loading Tool Cycle Time : Number of loading tool passes required to fill truck : 3 passes <br />Excavators and front shovels -machine cycle time vs. job condition rating : NA <br />- selected value within basic rating : NA <br />Track loaders - material descr.: NA <br />- cycle time elements (min.) : Load <br />NA Maneuver : NA Dump : 0.100 <br />Wheel and track loaders - unadjusted basic loader cycle time ( load, maneuver, and dumr 0.575 minutes <br />Cycle Time Factors Loading Condition Description Factor (min.) Source <br />Material : No adjustment - factor not applicable 0.000 (Cat HB) <br />Stockpile : Conveyor or dozer piled 10 ft. high and up 0.000 (Cat HB) <br />Truck ownership : Common ownership of trucks and loaders -0.040 (Cat HB) <br />Operation : Constant operation -0.040 (Cat HB) <br />Dump target : Nominal target 0.000 (Cat HB) <br /> Net cycle time aojustment : -0.080 minutes <br /> Adjusted loader cycle time (total time per loader pass) : 0.495 minutes <br /> Net load time per truck * : 1.090 minutes <br />Truck Cycle Time : *bulk of 1st loader cycle completed during truck exchange if adj. loader cycle time < exchange time <br />Truck exchange time **: 0.50 minutes........ Adjusted for site altitude : 0.500 minutes <br />Truck load time: 1.090 minutes........ Adjusted for site altitude : 1.185 minutes <br />Truck maneuver and dump time: 0.90 minutes........ Adjusted for site altitude : 0.900 minutes <br />** set at 0 if exchange time < adj. loader cycle time (truck exchange completed during tsl loader cycle) <br />Truck travel (haul & return) time: Road condition : Rutted dirt, little maintenance, no water, 2" tire penetration <br />Haul route : <br />Road <br />segment# Haul distance <br />(feet) Grade <br />res. (%) Rolling <br />res. (%) Total <br />resistance (%) Speed <br />(feet/minute) Travel time <br />(minutes) <br />1 4,500 0.00 5.00 5.00 1867 2.491 <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br />Keturn route : Haul time ** : 2.491 minutes <br />minutes <br />minutes <br />Loading tool unit production : 532.86 LCY/hour...... Adjusted for job efficiency : 442.27 LCY/hour <br />Truck unit production : 133.60 LCY/hour...... Adjusted for job efficiency : 110.89 LCY/hour <br />Optimal no. trucks/loading tool : 4 trucks........... Selected no. trucks/loader : 4 trucks <br /> Adjusted hourly truck team production : 443.56 LCY/hr <br /> Adjusted hourly single truck/loader team production : 442.27 LCY/hr <br /> Adjusted hourly multiple truck/loader team production : 442.27 LCY/hr <br />JOB TIME AND COST <br />Fleet size : 1 Team(s) Total job time : 6.33 Hours <br />Unit cost : $1.338 /LCY Total job cost : $3,746 <br /> <br />travel time shown for each segment includes acceleration/deceleration adjustment Return time**: 1.643 <br />total haul and return time shown includes altitude adjustment Total truck cycle time : 6.720