Laserfiche WebLink
phase. Once the interior area becomes small enough where the 2H:1 V mining slopes from three <br />to four sides are encroaching upon the portable plant and haul roads another phase will be <br />opened to continue mining. The slurry wall is anticipated to be installed prior to Phase 3 or at <br />some point between Phase 3 and 11 and it is expected minimal dewatering will be required in <br />the subsequent phases due to the slurry wall cutting off groundwater infiltration into the pit. <br />Journey Ventures, LLC will have an approved substitute water supply plan and well permit prior <br />to exposing groundwater. The substitute supply plan will be updated annually to account for <br />water that is consumed due to exposing groundwater by the mining operation. <br />Explosives <br />Explosives will not be used during mining. <br />M Journey Ventures, LLC. <br />UT Consulting, inc. Journey Ventures Pit <br />V DRMS 112 Permit Application