I ~ (MR06-207) <br />RECLAMATION COST ESTIMATE <br />Remove 2 modular E-Co containers <br />Labor (disconnect piping and electrical connections) est. 6 hrs @ $20/hr <br />Crane (load containers) est. 4 hrs @ $260/hr <br />Container removal (3,200 cf + 15,000 ct) 18,200 cf @ $.20/cf <br />$ 120 <br />$1,040 <br />$3,640 <br />Subtotal: $4,800 <br />Demolish and dispose of concrete slab and 4 concrete piers <br />Container 1 - 25' x 25' monolithic slab <br />(approx 16 cy, includes 4 concrete piers for container # 2) x $6.68/cy <br />Regrade pad area (included in dewatering facility reclamation cost) <br />Seeding (included in seeding costs for surface facilities area) <br />Powerline Removal <br />200 if x $2.03/If <br /> <br />Indirect and Administrative Costs (8'70) <br />Project Total Cost <br />C <br />MR06-207 <br />Subtotal Direct Costs <br />120 <br />$ 107 <br />$ 406 <br />$5,313 <br />425 <br />$ 5,738 <br />04/24/06 <br />