Laserfiche WebLink
4. Rail Spur and Rail Yard. A rail spur leading from the main rail line into the plant <br />area has been completed, including tying this spur into the main rail line and the plant rail yard. <br />Final activities include erosion stabilization and reclamation of any remaining ground <br />disturbance associated with construction of the rail spur. Construction of the plant rail yard is <br />mostly complete. Final tasks include stabilization of the side slopes of the rail yard, erosion <br />stabilization and reclamation of any of its remaining construction-related ground disturbances. <br />GCC anticipates that the majority of such remaining work related to the rail spur and rail yard <br />will be completed during the first calendar quarter of 2009. <br />C. COMPLIANCE WITH ALL EXISTING PERMITS AND AUTHORIZATIONS <br />GCC believes it is in compliance with all applicable requirements. <br />DN:32128119.2