U] <br />• <br />• <br />Table E-3 Reclamation Timetable <br />Description Time Needed (months) <br />Mine Phase 1. 7.9 <br />Reclaim Phase 1, and mine Phase 2. 10.9 <br />Reclaim Phase 2, and mine Phase 3. 8.5 <br />Reclaim Phase 3, and mine Phase 4 9.4 <br />Reclaim Phase 4, and mine Phase 5 9.5 <br />Reclaim Phase 5, and mine Phase 6 9.5 <br />Reclaim Phase 6, and mine Phase 7 7.2 <br />Reclaim Phase 7 0.5 <br />Remove facilities and pull pit pump & <br />reclaim areas <br />0.1 <br />Total (Months) 63.69 <br />Total Years 5.31 <br />White River City Pit, August 08 E-4