f <br /> STATE OF COLORADO <br /> MINED LAND RECLAMATION BOARD <br /> DEPARTMENT OF NATURAL RESOURCES <br /> IN THE MATTER OF: Landowner' s Request for BOARD <br /> Reclamation Schedule, ORDER <br /> The GEC Strip Mine <br /> Revoked Permit No. C-81-037 <br /> TO: The Corley Company and all other persons engaged in or owning <br /> or controlling the property upon which lies the former GEC Strip <br /> coal mining operation located in portions of Sections 24 and 25, <br /> Township 20 South, Range 70 West, and portions of Sections 19 and <br /> 30, Township 20 South, Range 69 West, of the 6th P.M. , in Fremont <br /> County, Colorado. <br /> FINDINGS OF FACT <br /> Pursuant to the authority vested in the State of Colorado Mined <br /> Land Reclamation Board by C.R.S. 34-33-101 et. seq. , the Board <br /> hereby makes the following findings of fact: <br /> 1 . On August 25-26, 1993 , the Board held a Formal Public <br /> Hearing to consider a petition from Dr. W.D. Corley, Jr. and <br /> the Corley Company ( "Corley" ) for the establishment of a <br /> schedule of the activities associated with the reclamation <br /> of the GEC Minerals, Inc. GEC Strip Mine, Revoked Permit No. <br /> C-81-037. <br /> 2 . Corley presented evidence and/or testimony at the Formal <br /> Hearing that: <br /> a.- - Corley was the lessor of the property upon which GEC <br /> Minerals, Inc. operated the GEC Strip Mine from 1975 to <br /> 1983, <br /> b. The Colorado Mined Land Reclamation Division ( "the <br /> Division" ) permit issued to GEC Minerals was <br /> subsequently revoked, and the associated performance <br /> bond forfeited in 1987; <br /> C. The Division is scheduled to begin reclamation of <br /> certain GEC Minerals disturbance in Section 24, T20S, <br /> R70W, in September, 1993 ; <br /> d. Reclamation of the area in Section 30, T20S, T69W known <br /> as the East Pit has yet to begin; <br /> e . Monies from the forfeited GEC Minerals performance bond <br /> that would remain following the reclamation scheduled <br /> for Section 24, T20S, R70W would be insufficient to pay <br /> for backfilling completely the East Pit with material <br /> from the adjacent material stockpile known informally <br />