March 1, 1995 <br />On some occasions, after approval by the Project Manager, payment may be made on account of <br />materials not incorporated in the work but delivered and suitably stored at the site, or at some other <br />location agreed upon in writing,. Such payments shall be conditioned upon submission `by by the <br />Contractor of bills of sale or such other procedure as will establish the Principal Representative's title <br />to such material or otherwise adequately protect the Principal Representative's interest, including <br />applicable insurance. <br />The Division of Minerals and Geology will accept original invoices only. Change order amounts and <br />retainage must be invoiced separately from items included in the original contract. All invoices, except <br />the final invoice, and the payments thereunder, shall be subject to correction in the next invoice <br />following the discovery of any error. <br />State law and regulations provide that contractors will be paid within 45 days after receipt of a correct <br />invoice. A State liability not paid within 45 days is considered delinquent and, unless otherwise agreed <br />to, interest on the unpaid balance shall be paid beginning with the forty-sixth day at the rate of one <br />per cent per month on the unpaid balance until paid in full. a liability shall not arise if a good faith <br />dispute exists as to:.the agency's obligation to pay all. or a portion of the liability. Contractors shall <br />invoice separately for interest on -delinquent amounts due. The billing shall reference the delinquent <br />payment, the number of days interest to be paid and the applicable interest rate. (24-30-202(24), <br />C.R.S. as amended) <br />Article 48. PAYMENTS WITHHELD <br />The Project Manager or the Principal Representative may hold, or, on account of subsequently <br />discovered evidence, nullify the whole or any part of any invoice on account of: <br />(a) Defective work not remedied; <br />(b) Claims filed or reasonable evidence indicating probable filing of claims; <br />(c) Failure of the Contractor to make payment to subcontractors or for material or labor; <br />(d) A reasonable doubt that the Contract can be completed for the balance of the contract <br />price then unpaid; <br />(e) Damage to another Contractor; <br />(f) Failure to obtain necessary permits or licenses or to comply with applicable laws, <br />ordinances, codes, rules or regulations; <br />(g) Failure to submit weekly progress reports; <br />(h) Failure of the Contractor to keep his work progressing in accordance with his time <br />schedule; <br />(i) Failure to keep a superintendent on the work; <br />(j) Unauthorized deviations by the Contractor from the Contract Documents. <br />When the grounds for such withholding or nullifying are removed, payment shall be made for the <br />amounts withheld. <br />If the Principle Representative deems inexpedient the correction of damaged work or of work not <br />performed in accordance with the contract, equitable reduction of contract price shall be made. <br />Article 49. FINAL INSPECTION <br />The Project Manager shall make final inspection of the project to determine whether the work has been <br />completed in accordance with the Contract Documents. A final punch list shall be made by the Project <br />Manager on the Final Inspection and Certificate of Completion form in sufficient detail to fully outline <br />to the Contractor: <br />a) Work to be completed, if any; <br />b) Work not in compliance with the drawings or specifications, if any; <br />c) Unsatisfactory work for any reason, if any. <br />DMG-17