March 1, 1995 - <br /> If any punch-list results from the final inspection, the Contractor shall promptly rectify all items on it. <br /> Article 50. FINAL INSPECTION AND CERTIFICATE OF COMPLETION <br /> The Final Inspection and Certificate of Completion shall establish the completion date of the project. <br /> Article 51. SETTLEMENT <br /> The Principle Representative shall not authorize final payment until all items on the punch list have been <br /> completed, the Final Inspection and Certificate of Completion issued, and the Notice of Contractor's <br /> Settlement published. Before the Principal Representative may advertise, the Contractor shall deliver <br /> the Project Manager all guaranties and warranties, and daily or weekly Job Logs. <br /> When the Principle Representative indicates acceptance of the work, the Contractor may requisition <br /> final payment, including retainage, on account of the contract price. <br /> Before such final payment may be made the Principle Representative must comply with Title <br /> 38-26-107 C.R.S. as amended, which requires that publication of a notice of final settlement with the <br /> Contractor be made twice in a newspaper of general circulation in the county wherein the purchase <br /> order contract was made (usually Denver County) and the county wherein the work was performed. <br /> The date fixed in such notice, before which final payment to the Contractor may not be made, must <br /> be no less than ten days after the second publication of the notice. <br /> Any unpaid creditor of the Contractor who supplied labor a d/or material for the work has those ten <br /> days in which to file with the Principle Representative a verified statement of the amount due and <br /> unpaid. The Principle Representative must withhold from payment to the Contractor the total amount <br /> of such claim for a period of ninety days after the date in Ithe notice fixed for settlement, but the <br /> Principle Representative may not directly make payment to the creditor(s). If within those ninety days <br /> a creditor does not reach settlement with the Contractor, he r ust file with the Principle Representative <br /> a notice that he has brought action at law, otherwise the Principle Representative, at expiration of <br /> ninety days, will pay the Contractor for the amount withheld. <br /> Article 52. GUARANTY AND WARRANTIES <br /> The Contractor shall furnish the Principle Representative with a written guaranty for one year covering <br /> all labor, materials and workmanship incorporated in the work. The Contractor, in instances of work <br /> performed or material or equipment furnished for which warunties are required by the specifications, <br /> shall procure such warranties and deliver them to the Principle Representative on completion of the <br /> work. Such warranties will no way lessen the Contractor's ;responsibilities under the purchase order <br /> documents. Whenever warranties or guarantees are required by the specifications for a period longer <br /> than one year, such longer period shall govern. Written gua anties must be received by the Principle <br /> Representative before final payment will be approved. <br /> Article 53. ASSIGNMENT <br /> The Contractor shall not assign the whole or any part of this Contract as any moneys due or to become <br /> due hereunder without the written consent of the Principal Representative. No assignment without <br /> said prior approval shall be valid. In case the Contractor assigns all or part of any moneys due or to <br /> become due under this Contract, the instrument of assignment shall contain a clause substantially to <br /> the effect that it is agreed that the right of the assignee in aid to any moneys due or to become due <br /> to the Contractor shall be subject to all claims of all persons, firms, and corporations for services <br /> rendered or materials supplied for the performance of the work called for in this Contract, whether said <br /> service or material were supplied prior to, or after the assignment. <br /> Article 54. LIENS <br /> There is no right of Mechanic's Lien against publicly-ow ed property in the State of Colorado. <br /> However, as outlined in Article 51 SETTLEMENT, unsatisfied creditors of the Contractor, for labor <br /> and/or materials, of such property are by law provided certa n alternate remedies. <br /> DMG-18 <br />