Laserfiche WebLink
Measurement and Payment <br /> There will be no measurement for Task#14. Payment for Task#14 will be reflected in a lump <br /> sum bid under Item #14 on the Bid Schedule. <br /> PROJECT OBSERVATION <br /> The PROJECT MANAGER will be at the project site periodically to monitor construction <br /> activities and ensure that each work item is completed and constructed to design <br /> specifications. The PROJECT MANAGER will be available during regular business hours (8:00 <br /> A.M. to 5:00 P.M.) on weekdays. Inspections will snot be scheduled on weekend days or <br /> holidays without prior approval of the PROJECT MANAGER. The following items must be <br /> observed and approved by the PROJECT MANAGER before proceeding with additional work: <br /> 1 . Task 6: grade of culvert prior to covering; <br /> 2. All final grading before the commencement of revegetation; <br /> 3. Fertilization; <br /> 4. Seeding, and, <br /> 5. Tubling planting <br /> 12 <br />