Laserfiche WebLink
TRUCK LOADOUT PROJECT- RECLAMATION COST ESTIMATE (TR06-53) <br />Facilities Demolition and Removal <br />Remove truck loadout equipment and conveyor structure (crane and operator, tractor-trailer <br />w/driver, and laborers) - 6 days x $1,620/day $10,120 <br />Demolish truck loadout building - 40 x 40 x 85 feet x $0.26/cf 35,360 <br />Demolish reclaim and escape tunnels - (10 fr dia. - 240 ft x $90/lf) + <br />(42 in. dia. - 140 ft x $35/lf) 26,500 <br />Demolish concrete slabs, foundations, piers, and caissons -110 cy x $445/cy 48,950 <br />Remove culverts - 801f x $9.30/lf (18"culvert) 744 <br />Subtotal $121,674 <br />Backfilline and Rep-rading <br />Backfill reclaim tunnel - 6,000 cy x $0.85/cy $ 5,100 <br />Regrade truck loadout pad azea - 3.1 acre x $1,200/ac 3 72 <br />Subtotal $ 8,820 <br />Topsoil Replacement and Reveeetation (included in costs for mine facilities area reclamation) <br />Subtotal -Direct Costs $130,494 <br />Indirect and Administrative Costs (8%) 10,440 <br />Proiect Total Cost $140,934 <br />Notes: Costs from Means Site Work and Landscape Cost Data and recent bond calculations <br />TR06-53 ~ 2 / 05/03/06 <br />