NMD (Panels 12-Right through 16-Right)(PR 99-OS) <br />TCC will continue to mine the reserves it controls in the Twentymile Park Basin. The mine will move its operation <br />mto the Northern Mining District as shown on Map 23, Mine Plan Map. TCC controls all of the coal required to <br />mine in this area. TCC projects annual coal production at 10 million tons per year. <br />TCC uses the longwall mining method as the primary technique for ensuring maximum recovery of the resource. It <br />is planned to install a 1,000-foot wide face, with panel lengths ranging from approximately 13,600 to 17,000 feet in <br />the Northern Mining district during this permit term. The gateroads, main and submains will be developed by <br />continuous miner, as is the current practice. <br />NMD -14-Right Gateroad Alternate Location (MR O1-171) <br />Currently, TCC is in the process of evaluating if the 1,000-foot wide face can be increased to approximately 1,200 <br />feet or wider. The outcome of the evaluation may limit the face width to something less than 1,200 feet. In order <br />to accommodate this uncertainty, and initiate the start of the gateroad, an area is shown in red on Map 23 and 23 B <br />for potential area in which the 14 Right Gateroad will be started. In the event that the evaluation determines that <br />the 1,000-foot wide face is the correct width for TCC's conditions, the location of the gateroad shown on Maps 23 <br />and 23 B will be followed. <br />NMD (Panels 17-Right through 21-Right, PR03-06) <br />TCC will continue to mine the reserves it controls in the Twentymile Park Basin. The mine will continue its <br />operation into the Northern Mining District as shown on Map 23, Mine Plan Map. TCC projects annual coal <br />production to increase from the current 10 million tons per year to approximately 12 million tons per year. <br />TCC uses the longwall mining method as the primary technique for ensuring maximum recovery of the resource. <br />In Panels 17- through 21-Right, mining will continue in the Northern Mining district during this permit term with a <br />1,000-foot wide panel and panel lengths ranging from approximately 10,900 to 15,700 feet. The gateroads, main <br />and submains will be developed by continuous miner, as is the current practice. <br />NMD (Panels 21-Right through 25-Right (24- and 25- Right Partial), PR06-07) <br />TCC will continue to mine the reserves it controls in the Twentymile Park Basin. The mine will continue its <br />operation into the Northern Mining District as shown on Map 23, Mine Plan Map. TCC projects annual coal <br />production of approximately 12 million tons per year. <br />TCC uses the longwall mining method as the primary technique for ensuring maximum recovery of the resource. <br />In Panels 21-through 24-Right, mining will continue in the Northern Mining district during this permit term with a <br />1,000-foot wide panel and panel lengths ranging from approximately 9,500 to 15,700 feet. The gateroads, main and <br />submains will be developed by continuous miner, as is current practice. <br />WMD (Panels 15-Left through 18-Left -Initial Development of Mains and Submains, PR06-07, TR07-63) <br />In preparation for future mining in the Western Mining District (WMD), TCC will proceed with initial development <br />of the main and submain entries for Panels 15-Left through 18-Left, as shown on the Mine Plan Map, Map 23. <br />Alignment of development entries may be adjusted, as necessary, to address geologic conditions. Main and <br />submain entries will be developed by continuous miner, as is current practice. <br />(2) Operation description. A general description and appropriate map(s), prepared in accordance with 2.10, <br />describing the area of land to be affected over the life of operation, according to the anticipated sequence of mining <br />and reclamation, and identifying each area of land for which it is anticipated a new, separate, five-year permit will <br />~be obtained and a performance bond will be posted throughout the operation and any change in a facility or feature <br />shown under 2.10 which would result from the proposed operations. <br />2.05-2.1 09/14/07 <br />TR07-63 <br />