Laserfiche WebLink
Grisenti Farms Gravel Pit <br />2008 Annual Report <br />Castle Concrete Company <br />M-2001-005 <br />Overview of Permit Year: During the 2007-2008 operating year mining continued in the <br />Phase 1 area as normal in a westward direction. Phase 1 is close to completion and plans <br />have been made to move the operation to Phase 2 in the next few months. <br />Annual Report Map: The annual report map included in the report shows the current <br />affected lands. <br />Affected lands: Affected land has increased in the Phase 1 area as depicted in the map. <br />Reclamation: As areas in Phase 1 have been completed they have been sloped and seeded. <br />Expected Activity: Mining is scheduled to move to the Phase 2 area in the next few <br />months. Phase 1 will be reclaimed and prepared for final land use.