5.0 SEDIMENT POND <br />The Northfield Project site sediment pond was designed to effectively treat the run-off from the 10- <br />year, 24-hour storm event. The pond was designed utilizing the SEDCAD4 computer model. The <br />input parameters and results are shown on the SEDCAD4 printout located in the Appendix B. <br />Sediment pond SEDCAD4 results are summarized in Table 3. <br />The location of the pond and its corresponding subwatersheds are shown on the Site Drainage Map. <br />Details for the sediment pond are located on the Sediment Pond Details sheet attached. A simplistic <br />approach was taken in determining disturbed area contributing to run-off. All areas which could <br />possibly be disturbed during the life of the project were considered disturbed for the sediment pond <br />design. These areas included the acreage below the run-on diversion ditches and above the run-off <br />collection ditches. Additionally, no sediment control barriers were used in the sedimentology design <br />of the pond. This approach resulted in a conservative design for the pond sediment storage design. <br />The sediment pond contains a principal and emergency spillway. The principal spillway has a 3-foot <br />tall perforated riser. The riser will be enclosed with a trash rack screen to prevent clogging and pass <br />the 10-year, 24-hour storm event without use of the emergency spillway. The principal spillway will <br />also allow for approximately 0.19 ac-ft of dead pool storage (not counting unused sediment storage <br />volume) to treat mine dewatering flows. The dead pool storage will allow for approximately 1.5 <br />days of dewatering flow retention. The emergency spillway consists of a trapezoidal cha~mel with <br />3H:1V side slopes. The spillway crest and outlet slope will be armored. The emergency spillway is <br />designed to safely pass the peak flow from the 25-year, 24-hour storm event while maintaining 1-foot <br />freeboard from the top of the pond embankment. The spillway is conservatively designed assuming <br />the principal spillway is clogged during the storm event. <br />The sediment pond will have a volume of less than 20 ac-ft as measured from the invert of the <br />emergency spillway to the bottom of the pond and the pond embankment will be less than 10 feet in <br />vertical height from the crest to the original ground surface. The embankments will be constructed <br />with 3H:1 V slopes and a top width of 15 feet. The embankment crest and outer slopes will be <br />vegetated with an approved native grass seed mix. During final design of the sediment pond, <br />analyses shall be performed to verify stability of pond embankment slopes for construction. <br />6.0 CHANDLER CREEK CROSSING <br />' The site access road will originate from Fremont County Road 79 and will cross Chandler Creek. <br />The headwaters of the Chandler Creek drainage basin are approximately 10,000 feet in elevation and <br />can receive substantial amounts of snow, potentially generating early spring run-off flows. The <br />' drainage basin is also over 11,000 acres in size. It would be anticipated that significant flows are <br />periodically produced by localized, high intensity rainfall events within the basin. <br /> <br />1 <br />r <br />~ ' <br />