Critical Path for Implementation of CERF <br /> Step Task Who By <br /> When? <br /> 1 Develop budget proposal SMc 7/7/97 <br /> 2 Develop Statutory Amendment proposal SMc <br /> 3 Get initial buy-in of CMA SMc 7/15/97 <br /> 4 Get approval of MEGA Board SMc 7/16/97 <br /> Get approval of MLRB SMc 8/27/97 <br /> 6 Complete information collection on Coal Gulch, La Plata, Sunbelt, LPR, 9/30/97 <br /> and Healy mine sites HBR, <br /> DIH, <br /> KAG <br /> 7 Develop Remediation proposals and cost estimates, assume: <br /> Hawks Nest(priority 1) DAB 10/1/97 <br /> WJC <br /> Amess-McGriffin(priority 1) LPR 10/1/97 <br /> HBR <br /> GEC (priority 1) DAB 10/1/97 <br /> l <br /> SLB <br /> Jewel (priority 2) DIH 10/1/97 <br /> KAG? <br /> Sunlight(priority 2) LPR 10/1/97 <br /> ESC <br /> 8 Inspect sites with AML to determine effectiveness of reclamation DL i 7/21- <br /> to meet Title V performance standards: Jlvfc 25/97 <br /> Healy, Blue Flame, TBM,New Pryor, Coal Gulch, S c <br /> La Plata, Sunbelt, Jewel, GEC, Arness-McGriffin, DI <br /> and Sunlight LPR - <br /> DAB <br /> et. al. <br /> 9 Seek legislative sponsors MBL 12/15/97 <br /> SMc <br /> 10 Set final priority and select projects for FY 1998/99 contracts AML 1/l/98 <br /> Coal <br /> 11 Get legislative approval of statutory amendment and appropriation MBL 5/15/98 <br /> SMc <br /> 12 Submit statutory amendment to OSM for program approval SLB 6/1/98 <br /> 13 Bid out contracts and begin projects AML 7/l/98 <br />