For J. A. Kiger July 15, 1996 <br />WEST PIT EXCESS SPOIL FILL CONSTRIICTION UPDATE AND CERTIFICATION <br />During the quarter beginning April 1, 1996 and ending June 30, 1996, I <br />inspected the area in which the West Pit Excess Spoil Fill is being constructed. <br />The purpose of these inspections was to inspect the areas currently being dumped <br />complete by the truck/shovel fleet; inspect the progress of the water monitoring <br />well drilling; inspect the topsoil lay down areas; inspect the fill for areas of <br />water seepage or surface drainage and to satisfy the requirements of CDMG Rule <br />4.09.1(lla). <br />During the inspections it was observed that the truck dump had advanced to <br />the point that the 7250 contour was nearly dumped in. Some of the dumping during <br />the quarter had occurred on the north east corner of the fill, some sloping had <br />been done in preparation for topsoil activities. (See photographs 93 and 94) <br />During the quarter the vegetation on the fill began to grow, and the <br />vegetation came in fairly well. (See photographs 95 through 99) <br />On June 25, 1996, the West Pit Fill MOnitOring Well was Completed. The <br />well was located on the 6950 bench and was drilled down through the rock <br />underdrawn. The total depth of the will was 90.5 feet. The location of the well <br />and the casing above the fill is shown in photograph 100. <br />Attached to this report are my certification that all construction <br />requirements have been met thus far in constructing the West Pit Excess Fill. <br />c~~~ ~ <br />Stephen R. Hinkemeyer <br />Sr. Mining Engineer <br />c.c. central files <br />