After construction, the West Pit Fill will be monitored <br />quarterly for the following items and reports will be submitted in <br />the Annual Reclamation Reports. <br />1. The groundwater piezometer well will be established in <br />the valley bottom and will be monitored quarterly for <br />water level and the other parameters consistent with the <br />present Colowyo groundwater monitor plan. Fora proposed <br />location of the well see the attached map. <br />2. On a quarterly basis the survey monuments on the face of <br />the fill will be monitored for horizontal and vertical <br />movement. For the proposed location of the monuments, <br />see the attached map. <br />3. On a quarterly basis a certified report by a registered <br />engineer will be completed taking into consideration any <br />changes in the results of items 1 and 2 above and will <br />note any evidence of surficial slope failure or the <br />formation of springs or seeps on the face of the fill. <br />