<br />This revised plan outlines the use of the modified in-situ <br />technology developed by Occidental 011 Shale, Inc. for recovering oil <br />from the shale. The following are important milestone events for this <br />revised development plan. <br />September 1977 Mobilization and Start of Shaft Sinking <br />April 1979 Begin Construction of Initial Retorts <br />May 1980 Ignite Initial Retorts <br />September 1982 Start Full-scale Operation <br />The project is expected to have a capital cost of $443 million <br />and create 1600 permanent jobs prior to reaching full capacity of <br />57,000 Bbl/day in 1983. <br />-4- <br />