<br />January 7, 1992 <br />To: G.C. Dodson <br />From: J.C. Lenz <br />Subject: December Monthly Operating Report <br />Mill Operations <br />1.1 Crushing <br />Approximately 100,358 wet tons of ore were crushed <br />in December. operating availability of the primary <br />crusher declined to 71.6$. The grizzly was removed and <br />taken to the shop to be rebuilt. Numerous times large <br />rocks and/or frozen fines plugged the crushing system. <br />Blasting to remove hang ups contributed to the premature <br />failure of some wear plates in the dump bin. <br />Approximately 250 feet of CV-O1 were sliced by a wear <br />plate that was dislodged from the ROM bin. Rectifiers in <br />the variable frequency drive on the vibrating feeder <br />failed on the 24th and again on the 27th. The cause for <br />the failures may be a short to ground in the wiring. <br />1.2 Grinding <br />118,927 dry tons of ore were ground during December. <br />Operating availability of the plant decreased to 84.6$ <br />this month. Average plant throughput for the month <br />decreased to 188 tons per hour. Total power consumption <br />increased to 36.2 kwh/ton. The mass flow tonnage was <br />adjusted to account for the time the thickener was in <br />recirculation mode. The negative adjustment Was 9,425 <br />tons. <br />Unscheduled mill downtime was excessive during the month. <br />A detailed description of the events is contained in a <br />