Laserfiche WebLink
EASTSIDE MINE <br />Water Monitoring Program <br />Baseline surface water quality was obtained in September 1983 with a full suite of chemical parameters <br />analyzed. Additional surface and underground hydrologic sampling was analyzed for a full suite of <br />chemical parameters in April 1984. Eastside's hydrologic monitoring program was initiated in July 1984. <br />Surface and underground field parameters were measured, and samples for chemical parameters were <br />collected as defined by Stipulation 1 of the Mining and Reclamation Permit, C-84-063, approved January <br />14, 1985. Due to a large reduction in flow, monitoring of the two underground wells and seep was <br />eliminated. After three yeazs of quarterly sampling with no significant deviations or variations of the <br />chemical parameter, sampling of the surface water was reduced from quarterly to semi-annual basis. <br />The present surface sampling pourts are: 1-Harvey Gap Outlet-Above Mine; 2-Harvey Gap Outlet-Below <br />Mine; 3-Seep below Harvey Gap Reservoir. The ground water sampling point is the four inch pipe <br />installed through the mine portal seal to discharge water from the mine if the water level should rise <br />sufficiently in the underground workings of the mine. To date no discharges have occurred from the mine. <br />The Geotech WeII, the sampling point for the proposed location for the waste disposal, was reclaimed <br />in June of 1995. <br />The water monitoring program was initiated by Stephen Self, General Manager. Current monitoring is <br />performed by Stephen Self. Samples for the full suite of chemical pazameters aze shipped to ENVIRO- <br />CHEM Laboratory in Grand Junction, Colorado for analysis. <br />Page 1 of 22 <br />