Laserfiche WebLink
i.e. continuous miners and shuttle cazs. Following commissioning of the shaft, the shaft pad site and <br />access road will be cleaned-up and surface areas graded and dressed. <br />No. 7 North Escape Shaft (Section 20, TSN, R86V1~ <br />A 1,066 foot escape borehole shaft was constructed into the No. 7 entry of North Mains to allow <br />emergency evacuation of personnel from the development sections of the 9-Right and 10-Right gateroads. <br />The construction of the shaft utilized raise drilling techniques. It is anticipated that the escape shaft will <br />be utilized for approximately ten yeazs. The site is shown on Figure 23, General Location of Escape <br />Shaft. <br />The drilling of the shaft resulted in minimal surface disturbance. A drill pad approximately 200 x 200 <br />feet was constructed at the resulting site in 1,450 CY of cut and fill. Available topsoil was salvaged and <br />stockpiled for future reclamation of the site immediately northeast of the drilled pad. Approximately 18 <br />inches of topsoil derived from Cochetopa Loam is available for salvaging (222 CY). Casing and other <br />drilling supplies were stockpiled on the borehole pad. <br />After topsoil removal, two mud pits 10 x 10 x 7.5 feet were dug adjacent to the drillhole. Drilling fluids <br />and cuttings were discharged into the adjacent pits, allowing settling in one pit, with water decanting into <br />the adjacent pit. Drilling muds were used during the course of drilling the surface collaz and pilot hole. <br />The surface collaz was approximately 5.0 feet in diameter, and the pilot hole was 11 inches in diameter. <br />The collaz was comprised of two components; a surface concrete pad and a liner or casing that extends to <br />bedrock. A concrete centering base is at the bottom of the liner. <br />The concrete pad was poured around the liner and was approximately 14x 10 x 2 feet, however, the liner <br />extends through the pad, reducing the amount of concrete needed to construct the pad. Approximately 8.9 <br />CY of concrete was required to construct the pad. <br />After the collaz and liner were in place and the pilot hole was completed, raise-boring methods were used <br />to complete the hole. The hole was reamed to a final diameter of 4.33 feet and a 48-inch diameter steel <br />casing was cemented in place from 50 feet below the bottom of Twentymile Sandstone to the top of the <br />concrete centering pad. The remainder of the casing below the cement hangs in the hole. The hole is <br />approximately 1,100 feet in depth. The 4-foot diameter casing extrudes 4 to 6 inches out of the concrete <br />surface pad. A cap to regulate intake air flow was installed. A fence was installed azound the drill pad to <br />prevent access by cattle, after completion of the hole. Access was derived from an existing light-use road <br />running up to an old electrical borehole. A series of culverts were placed under the existing road as <br />shown on Figure 23, General Location of Escape Shaft. The design for the culverts can be found in <br />Exhibit 8D, Escape Shaft/Light-Duty Road Culvert Design. TCC constructed an additional 25-foot wide <br />road at a 4 percent grade to access the site. The 1,300-foot long road is graveled with 0.5 feet of 6-inch <br />pit-run gravel. <br />Buffalo Force Fau Silencer (MR 03-1871 <br />A new silencer will be installed on the Buffalo fan at the NW Mains Ventilation Shaft location. <br />Installation of the silencer will require construction of foundations utilizing concrete piers and concrete <br />grade beams. The foundation will require eight concrete piers (6-inch radius x 20 feet deep) and then <br />placement of two concrete grade beams (12" x 2' x 31') on top of the piers. The concrete grade beams <br />will be reinforced with three #5 rebar, and #4 stirrups spaced at 8 inches on center within 3 feet of the <br />piers, and spaced at 16 inches on center at all other locations. <br />TROS-48 2.05-45.7 09/05/05 <br />