My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
PERMFILE129033
DRMS
>
Back File Migration
>
Permit File
>
300000
>
PERMFILE129033
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 10:26:07 PM
Creation date
11/25/2007 7:01:43 PM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1980244
IBM Index Class Name
Permit File
Doc Date
9/3/2002
Doc Name
Certification Report Weekly Summary No. 26
From
Cripple Creek & Victor Gold
To
DMG
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
41
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Phase IV Weekly Summary No. 26 Page 2 <br />Ames resumed clearing and grubbing in the Phase IVa area. <br />• Phase Nb <br />003-2203 <br />Ames continued placement and compaction efforts of SF, west of the active crusher, for the new <br />LOB construction. Ames placed SF in approximately 2-foot lifs, removed oversized and deleterious <br />material (roots), moisture conditioned, and compacted the fill that was borrowed from the Phase IVa <br />slope excavation and Phase IVb local borrow. Compaction was attained by use of a smooth dnun <br />vibratory compactor. <br />Confirmation drilling occurred on July 30`h, on underground working UG-296 within the Phase IVb <br />area. No laterals were located in these azeas. <br />Remediation excavation of UG-492 and UG-313 continued during this reporting period. Both UG- <br />313 and UG-492 were determined by excavation to be "Shallow" workings (less than 25 feet deep) <br />and were remediated by excavating to working termination and backfilled with compacted Structural <br />Fill. <br />Phase IVc <br />Caterpillaz D10 and D8 dozers grubbed and cleared topsoil from within the limits of the Phase IVc <br />area. A Caterpillaz 375 track-hoe loaded 777 end-dumps with the topsoil material, which was hauled <br />to a stockpile west of the Phase IVc limits. <br />• No confirmation drilling or underground remediation occurred in the Phase IVc azea during this <br />reporting period. <br />(See Attachment A for approximate construction locations for all Phase IV areas.) <br />Field Monitoring and Testing Activities <br />Golder observed clearing and grubbing activities in Upper Arequa Gulch and Phase IVc area. <br />Cleazing and grubbing activities were conducted within the clearing limits. <br />Golder monitored SF placement in the Phase IV azea including, verification of lift thickness, <br />material, compactive effort, particle size, and temperature for compliance with the drawings and <br />method specifications. No moisture/density tests were performed on SF during this reporting period, <br />as material was un-testable per ASTM D698, based on laboratory testing and visual determination. <br />Golder observed the removal of oversized and deleterious material from the fill. <br />Golder observed confirmation drilling and underground working excavation in Phase IVb (full time). <br />Golder observed excavation and backfilling of UG-313 and UG-492. Golder observed placement of <br />compacted Structural Fill. Structural Fill was placed in approximately 2-foot lifts and compacted <br />using a smooth drum vibratory roller and/or an excavator bucket. Backfill was placed in accordance <br />with specification completing remediation of these workings. <br />aiwe rv,umiyzv.,wea m~ Golder Associates Inc. <br />