In 1999, Colowyo submitted TR-49, which allowed for a modification to the West Pit disturbance <br />area. The TR-49 modifications added $31,876 to the previously calculated bond liability of <br />$15,670,521, for a total calculated liability of $15,702,397, leaving a remauvng contingency of <br />$297,603. <br />In 2001, Colowyo submitted TR-50, which transferred the bond surety for exploration activities from <br />the mine bond to an exploration bond. The TR-50 revision reduced the mine reclamation liability by <br />$30,823, resulting in a total calculated mine reclamation liability of $15,671,574 and a remaining <br />contingency of $328,426, based on bond liability coverage of $16,000,000. <br />In 2001, Colowyo also submitted TR-53, which extended mining into Section 17. In conjunction <br />with review and revision of the bonding calculations fox TR-53, an error was found in the topsoil <br />replacement costs in the previous bond calculations. With the appropriate correction of the bond <br />calculations to address this error, the TR-53 revision reduced the calculated mine reclamation liability <br />by $1,568,751 to $14,102,823. Given bond liability coverage of $16,000,000, the remaining <br />contingency amount increased to $1,897,177. <br />The TR-56 submittal in 2002-2004, addressed changes in the postmining topography and drainages <br />to reflect material balance and excess spoil considerations. The topographic changes, as well as <br />updates relative to mine pit and reclamation location and status, necessitated some minor changes in <br />the bond reclamation material movement volumes and distances. Revision of the bonding <br />calculations to reflect these changes and updated labor and equipment costs resulted in a total <br />calculated bond reclamation Gabihty of $19,171,621 (an increase of $5,068,798). Based on the revised <br />calculated bond reclamation costs and the current bond liability coverage of $16,000,000, Colowyo is <br />in the process of obtaining an additional $3,500,000 of bond liability coverage, resulting in a bond <br />contingency of $328,379. <br />Calculations of the reclamation bond amount, all associated plans and designs, cost documentation, <br />and summary table are included in Exhibit 13, Bonding Information. <br />Rule 3.02 3.02-3 Revision Date 3/31/04 <br />Revision No. TR-56 <br />