NORTHWEST COLORADO CONSULTANTS, INC. <br />•' <br />• <br />Project: Haul Road Y-B <br />Location: Hayden, Colorado <br />Client: Seneca Coal Company <br />Work Performed: <br />Project No.: 95-2384 <br />Report No.: 88 <br />Date: 8/22196 <br />Time: 2.6 <br />Mileage: 30 <br />Engr./Tech: JK <br />As requested, we visited the project site on this date to conduct nuclear density test No.'s 178 through 181 on the <br />material placed. <br />Excavation crews cut and placed on-site borcow material for the subgrade fill in the left lane from Sta. 43+00 to <br />Sta. 46+00, and in both lanes from Sta. 60+00 to Sta. 64+00. <br />Remarks: <br />The material tested generally met project specifications. Compaction ranged from 93% to 96% and moisture <br />contents ranged from 6.8% to 3.3% below optimum. <br />Chuck McCulloh, of Seneca Coal Company, was notified of today's test results. <br />Verbal Discussions: <br /> <br />