• Table 5-1 Trapper Mine Topsoil Plle Inventory (1) • •
<br />Topsoil
<br />Pile ID
<br />Location Coordinates
<br />North
<br />East Size
<br />(acres) Approximate
<br />CYDS Created
<br />Date
<br />A78-4 GB well ske 410,070 1,417,400 0.5 7,805 pre 1978
<br />A77-1 A fleki coal pile 409,850 1,411,300 1.3 12,944 8/77
<br />A88-1 North A Haul Road W of REA Line S 405,450 1,425,100 1.7 80,480 1988
<br />•A91-8 MR-111 Relocate MPB & A8 (1991) 410,800 1,421,400 5.1 80,859 1991
<br />'A92-1 North A Road East of East Pyeatt 411,900 1,427,900 12.5 338,429 1992
<br />A92-2 Middle Pyeatt Reprede Spoils 409,800 1,428,000 8.0 179,878 1992
<br />A92-3 North A Road Eest of West Pyeatt 412,100 1,424,400 0.8 7,832 1992
<br />A93-1 A pk South #1 408,550 1,428,040 3.9 88,454 1993
<br />A93-5 South A pk #5 408,920 1,428,580 4.3 94,588 1993
<br />A93-8 South A pk #B 407,200 1,429,280 4.4 24,088 1993
<br />A94-2 E of Grouse Drainage 412,000 1,429,300 4.4 115,230 1994
<br />A94-4 S otA pk cut 408,500 1,429,800 3.9 124,880 1994
<br />A95-1 South end ofA-Pk 407,100 1,413,920 5.1 188,054 1995
<br />A95-2 Oak Pond 410,400 1,433,030 1.1 13,548 1995
<br />A98-1 Mkt A Spoil Road 409,800 1,429,450 2.1 52,812 1998
<br />A98-2 North A Pk west ofA 95-2 411,100 1,432,100 3.0 87,480 1998
<br />A97-1 South A Pk East Skis of F4 Road 405,480 1,430,250 2.8 57,172 1997
<br />A97-2 South of LOM Road 408,150 1,429,200 1.5 87,920 1997
<br />A97-3 North end 97A-T/S Laydown 411,200 1,430,230 0.5 15,484 1997
<br />A98-1 F3 and F4 Road Intersection 407,070 1,430,520 2.8 42,478 1998
<br />A98-2 Middle A Road North Side 409,300 1,430,730 2.9 80,332 1998
<br />A98-3 West Middle Flume Pond #3 407,500 1,438,240 0.5 4,820 1998
<br />ASH1 Johnson Gulch Eest Tributary 408,000 1,421,200 3.9 97,092 1992
<br />ASH2 Johnson Gulch East Tributary 408,200 1,422,000 1.3 27,488 1992
<br />BUZ92-1 Far East Buzzard Pond #1 411,100 1,410,250 0.4 882 1992
<br />CG1 Coyote Gulch 411,050 1,412,200 4.8 18,309 5/78
<br />D87-1 D pk temp N. 405,500 1,413,100 1.0 7,438 12/87
<br />D92-1 Deer Pond #1 400,700 1,417,850 3.7 23,518 1992
<br />D93-1 North D pk #1 407,725 1,418,180 0.5 20,570 1993
<br />D98-2 Mkldle D Pk 402,880 1,415,890 4.3 59,840 1998
<br />D98-3 South D Pk 401,180 1,415,820 2.4 31,184 1998
<br />cont.
<br />~ ales
<br />
|