<br />Exhibit L <br />Reclamation Costs <br />• Revision k3-Page 20 of 30 <br />Reclamation of the project site will consist of importing fill material, approximately 650,000 cubic yards, <br />to replace the volume of sand and gravel mined from the site, such that it may be reclaimed back to its <br />original grades. Imported fill soils will consists ofnon-hazardous soil, concrete, rock, and brick such that <br />no single piece of material has a dimension larger than two (2) feet on any face. No material larger than six <br />(6) inches in diameter will be placed within the top two feet of the final grade. <br />To minimize the amount of reclamation bonding requved for the project, the applicant would limit the <br />excavation pit area (backfill area, sand and gravel highwall, and overburden highwall) to no more than <br />three acres. By limiting the size to three acres, the estimated volume of backfill material required to <br />reclaim the site is approximately 130,680 cubic yards. <br />The applicant has existing stockpiled material stored at the site that will be used for the mining operations. <br />At the present time 9,000 cubic yards of fill is stockpiled in a berm located at the southeast comer of the <br />site, and 9,000 cubic yards fill is stockpiled along the north property line. <br />The reclamation cost estimate assumes that a majority of the reclamation work requ'ved is located the <br />farthest point away from [he material stockpile locations. The estimate assumes the following: <br />3 Acres to be backfilled/compacted; <br />114,500 CY of fill will need to be required; <br />18,600 CY of fill is onsite (9,000 at north property line & 9,600 in Berrn at SE Comer of Site) <br />95,900 (Round to 96,000) CY of fill must be imported <br />32.5 total acres requires topsoil replacement; <br />32.5 Acres will be deep tilled prior to topsoil placement; <br />32.5 acres to be disked, mulched, seeded and fertilized; <br />Gravel haul roads and scale house to be demolished; <br />Settlement pond a[ 1 acre to be demolished; <br /># DESCRIPTION QUAN UNIT UNIT/$ TOTAL <br />1 Import Fill, Truck, Load, Dumped At Pit (5 mile) 96,000 CY $ 1.60 $153,600 <br />2 Haul/Place Onsite Fill (1/3 Mile Trip) 18,600 CY $ 0.50 $ 9,300 <br />3 Compact Fill 96,000 CY $ 0.20 $ 19,200 <br />4 Demolish Settlement Pond (1 Acre) 5,000 CY $ 0.50 $ 2,500 <br />5 Remove Haul Roads/ Scale Structure 1 LS $ 2,500.00 $ 2,500 <br />6 Deep Till Reclamation Area 32.5 AC $ 50.00 $ 1,625 <br />7 Topsoil Placement From Stockpile 17,500 CY $ 0.30 $ 5,250 <br />8 Mulch Site 32.5 AC $ 50.00 $ 1,625 <br />9 Disc Site 32.5 AC $ 100.00 $ 3,250 <br />10 Seeding 32.5 AC $ 100.00 $ 3,250 <br />11 Fertilize Site 32.5 AC $ 25.00 $ 813 <br />12 Weed Control 32.5 AC $ 100.00 $ 3,250 <br /> TOTAL $206,163 <br />