6.4.5 Exhibit E -Reclamation Plan <br />Reclamation summary <br />Reclamation proposes to backfill Cell 2 and Cell 3 close to historic grade. For <br />Cells 1 and 4, slopes will be graded from approximately 0.5H:1 V to 3H:1 V and be <br />to allowed to fill with water leaving a 69 acre lake occupying Cell 1 and the <br />existing lake area. Topsoil will be replaced to a depth of 0.25 to 0.5 ft for <br />excavated areas including lake freeboard, slopes of the relocated Plumb and <br />Dailey Ditch and all of Cells 2 and 3. <br />Reclamation of the Turnpike Mining Resource will occur concurrently with mining. <br />The general order of reclamation activities is given in Table 1, Reclamation <br />Sequence Summary. <br />Table 1 -Reclamation Sequence Summary <br />Reclamation Activity Reclamation Sequence <br />Backfill the west 250 ft of existing Pond During Mining of the North 1/3 of Cell <br />Backfill areas adjacent to Oil and Gas <br />Structures -North 1 /3 of Cell 1 <br />Backfill Cell 2 <br />Backfill Cell 3 <br />Final Slope Grading <br />Topsoil Replacement <br />Seeding and Fertilizing <br />During Mining of the North 1/3 of Cell <br />1 <br />Following Mining of Cell 2 <br />During mining of the southern 2/3rds <br />of Cell1 and following mining of Cell 4 <br />Following all mining activity <br />Following slope grading <br />Following Topsoil Replacement <br />Backfill Western 250 ft of Existing Pond <br />Reclamation will begin by moving overburden from the north 1/3 of Cell 1 to the <br />west 250 ft of the existing pond area. Backfilling this area will help to stabilize <br />the river bank of Boulder Creek and prevent river capture of the existing pond. <br />Total volume to backfill this area is approximately 65,000 yd3 <br />Concurrent Backfilling Adjacent to Oil and Gas Structures <br />Agreements between owners of oil and gas structures specify that mining can <br />occur as close as 10 ft from flow lines and 40 ft from oil and gas well facilities as <br />a temporary condition. ASCI will backfill areas adjacent to oil and gas facilities to <br />a distance of 25 ft from flow lines and 150 ft from oil and gas wells as shown in <br />Exhibit C -Mining Plan. Backfilling adjacent to oil and gas structures will occur <br />within two weeks following excavation near oil and gas structures. Total volume <br />of material needed to backfill this area is approximately 94,307 yd3 <br />Turnpike Mining Resource <br />Regular 112 application <br />