NORTHWEST COLORADO CONSULTANTS, INC. <br /> <br />Project: Pond E Relocation Project No.: 95-2505 Date: 11/18/95 <br />Time: 1.0 <br />Location: Foidel Creek Mine Report No.: 10 Mileage: 15 <br />Client: Precision Excavating EngrJTech: JK <br />Work Performed: <br />As requested. we visited the project site on this date to conduct nuclear density test No.'s 29 through 31 on the <br />material being placed. <br />The excavation contractor. Precision Excavating, placed and compacted 12' of imported 3' minus pit run material <br />for the subbase of the haul road B being constructed adjacent to the relocated Pond E. <br />Remarks: <br />The material tested generally met project specifications with moisture contents being 2.2% to 1.5% below <br />aoumum. <br />Please refer to the attached sheet for results of today's testing. <br />Verbal Discussions: <br />David Zehner of Precision Excavating was notified of today's test results. <br />