Surface Facilities Area
<br />• The sedimentation control structures associated with the portal area, Map 24, Surface Facilities, have been
<br />constructed in accordance with previously approved pemuts (CYCC Permit No. 79-177 and TCC Permit No. C-
<br />82-056). These structures include the following: 1) Pond D, 2) Pond E, 3) Pond F, 4) Pond G, and 5) their
<br />associated drainage ditches.
<br />An aerator was installed in Pond D to promote aerobic conditions throughout the yeaz. There is an existing
<br />powerline and power-box on the west side of the pond. The aerator and power supply will be removed prior to
<br />reclamation of the pond.
<br />All of the above sedimentation control structures have been addressed under Rule 2.05.6 below, with the exception
<br />of surface drainage modifications associated with the new coal-handling facilities. Drainage from these Facilities
<br />will be channeled to Pond D, Pond E, Pond F, and Pond G as shown on Map 24, Surface Facilities. Diversion ditch
<br />and culvert designs are included in Exhibit 8, Sediment Control Plan.
<br />Tn order to provide for better drainage from the west ramp of the portal, the system has been modified. The two
<br />culverts that carry water from the west ramp will be plugged, and the water will be diverted towazd the Wadge
<br />sump. These culverts have been deleted from Map 24, but still exist in the field. Water will flow to a small
<br />sediment dam which holds a 4-inch overflow pipe. Once the water reaches the top of the sediment dam, the water
<br />will enter the 4-inch overflow pipe and then drain to the sump. This system will aid in settling-out some sediment
<br />from the water before it reaches the Wadge sump. From the sump, the water will be pumped to Ditch D-2.
<br />Two water bodies, the Area 1 Pit Temporary Water Storage Basin and the Thickener Overflow Sump, utilized in
<br />conjunction with ongoing mine water handling operations, have existed for years and were not previously identified
<br />or considered as "impoundments" under the regulatory definition. As a result of changes in regulatory
<br />interpretation, however, the CDMG has detemrined that these existing water bodies fall under the broad definition
<br />of "impoundments" and should be identified and regulated as such. Because they are existing water storage
<br />facilities and were not specifically designed or constructed as impoundments, the applicable requirements of Rule
<br />4.05.9 are addressed in this context by the following descriptions and the referenced existing configuration
<br />drawings:
<br />Area 1 Pit Temporary Water Stora eg Basin -The Area 1 Pit is a remnant surface mine pit adjacent to the Run-of-
<br />Mine Coal Stockpile), as shown on Map 24, Surface Facilities, and by Figure EXSv-1 in Exhibit SV. Impoundment
<br />design, operation, maintenance, and reclamation information is provided in Exhibit 8v. The remnant pit azea is a
<br />totally incised excavation, enclosed by undisturbed natural ground and backfilled surface mine spoils, with an
<br />estimated maximum water storage capacity of approximately 200 acre-feet. The pit azea is used for temporary
<br />storage of excess mine water, as part of the closed-loop mine dewatering and recycle system. Water inputs to the
<br />pit aze limited to excess dewatering flows from the mine dewatering systems and minor incident precipitation. An
<br />upgradient diversion ditch (Ditch D-3) intercepts any surface runoff from upgradient reclaimed surface mine azeas
<br />and routes it azound the Area 1 Pit to Pond D. While a small culvert outlet at the low point on the crest of the pit
<br />allows for minor discharge flow to Pond D if the water reaches this level, the temporary storage basin is normally
<br />managed to keep water levels well below the discharge pipe. A fixed pumping station is used to control water
<br />level, with discharge to a de-sander, located at an old well site and then to the Coal Prepazation Plant or the mine
<br />water recycling system, or directly to Pond D for discharge to Foidel Creek. Management of the Area 1 Pit storage
<br />basin involves regular inspection and maintenance of water levels and pumping systems, and reduction of water
<br />levels prior to spring discharge to provide additional water storage capacity for any minor increases in subsequent
<br />spoil spring discharge.
<br />Thickener Overflow Sumn -The Thickener Overflow Sump, located adjacent to the Thickener Tank in the Coal
<br />Preparation Plant area, as shown on Map 24, Surface Facilities, and by Figwe EX8w-1 in Exhibit 8w was
<br />excavated during Preparation Plant construction to serve as a catch basin for the contents of the thickener, if
<br />required for maintenance or under upset conditions. Impoundment design, operation, maintenance, and reclamation
<br />information is provided in Exhibit 8w. While it has not been necessary to utilize the basin for this purpose, it is
<br />MROS-194 2.05-79 07/2/05
<br />
|