Laserfiche WebLink
2.05.4 -RECLAMATION PLAN <br />ABANDONMENT OF THE MINE: REMOVAL OF SURFACE FACILITIES <br />The following mine facilities and structures will be removed or demolished: <br />Mine portal facilities, shown on Map C-4, will be torn down. The foundations, <br />steel, and other non-woody material will be pushed against the highwalls and <br />covered by at least 4 feet of fill and plant growth medium as detailed elsewhere <br />in this section. Woody material will be moved to the burn pit near the lower <br />pump house and burned. Miscellaneous trash and debris (assume 150 cubic <br />yards) accumulated during final reclamation will be burned and buried. <br />• The Tipple Building is only a "snow shed", of pole barn construction, <br />essentially atin-covered wooden roof held up by several steel posts. This 60' x <br />65' structure has no walls and is 1 foot thick. <br />• The Tipple Shed measures 16' x 44' x 8', and is a wooden post and beam <br />construction. <br />• The Main Conveyor Portal Shed is very similar in construction to the Tipple <br />Shed. This shed measures about 12' x 20' x 8'. <br />• The Tipple Bin measures about 15' x 25' S0' and is entirely constructed of <br />steel beams and bolted plate. <br />• The Mine Fan is a prefabricated coal mine ventilation fan assembly made up <br />of three main parts. The fan is basically a 6' diameter skid mounted cylinder <br />about 16' long which unbolts from the fan housing. The fan housing is a 5' <br />diameter metal culvert which extends for several feet underground to connect <br />the fan to the mine workings. Adjacent to the fan housing is the escape <br />airlock unit which is a steel box with two sets of airlock doors. This steel box <br />measures about 6' x 8' x 8'. <br />• The Main Conveyor is elevated about 7' high and extends about 40 feet from <br />the mine portal, discharging into the Tipple Bins area. The structure <br />measures about 5' wide by 4' high. <br />• The Stacker Conveyor extends about 300' from the Tipple Bins azea to <br />Stacker Tower #1, supported about midway by Stacker Tower #2. <br />• Stacker Tower #1 is a 50' tall conveyor support tower of steel beam <br />construction. It measures 16' x 16' at the base and tapers to 10' x 10' at the <br />top, with a total volume of 8900 ft3. <br />• Stacker Tower #2 is a 25' tall conveyor support tower of steel beam <br />construction. It measures 8.5' x 16' at the base and tapers to 8.5' x 5.5' at the <br />top, with a total volume of 2284 ft3. <br />• Two 500 Gallon Diesel Tanks shown on Map C-4 are the property of the fuel <br />National King Coal, LLC King I Mine <br />Section 2.05.4 <br />Page 1 March, 2006 <br />Nlk-30 <br />