Laserfiche WebLink
<br />Revised Exhibit L, Reclamation Cost Estimate <br />In order to calculate maximum potential reclamation liability to the State, we have selected a point in <br />time where the mining disturbance could be at is maximum. This point occurs during the mining of <br />Phase II. At this time the mining face in the east/west direction will be at its greatest length. There will <br />be shoreline under reclamation in the Phase II area. The Phase I pit will be in use as a siltation pond and <br />the collected silt will be lefr in place as backfill. Please refer to page 5 for a listing of disturbed areas <br />that to[a145.4 acres. This estimate will follow the same order as the listing on page 6: <br />A. Stripped overburden and topsoil in anticipation of mining Qty Units Unit Cosf Cos! <br />1. Replace the overburden, 6" over 10 acres, 500 ft haul 8066 CY $ 1.25 $10,083 <br />2. Replace topsoil, 6" over 10 acres, 500 ft haul 8066 CY 1.25 10,083 <br />3. Seed and mulch 10 Ac 800.00 8,000 <br />B. Active mining area <br />1. Backfill Phase I siltation pond (l l feet over 13.2 acres) and <br />Grade 3:1 slopes to crest, silts provide 120,000 CY 183,150CY 1.50 275,000 <br />2. Provide pit dewatering for %: pit volume, 23.2 acres, 9 feet 68 MG 201.50 13,702 <br />3. Pit Liner- install, repair, or replace 20% 2,690 LF 77.90 209,500 <br />C. Topsoil and overburden stockpiles <br />1. See Item G below for the costs as these materials <br />will be used for backfilling <br />D. Dewatering trench <br />1. Dozer soil into trench, 500' length at 32'deep, 50' push <br />2. Replace topsoil, 6" over I acre, 500 ft haul <br />3. Seed and mulch <br />E. Mining face, 2000 ft across Phase 77 <br />1. Backfill mining face to 3:1 slope, 500' haul <br />2. Replace topsoil above waterline, 6" over 2.3 acres <br />3. Seed and mulch <br />F. Roads <br />1. Roads for access, along Fulton Ditch, and around <br />reservoir will remain in place. <br />C. Side slope undergoing backfilling and grading, 600 ft <br />I. Backfill to 3: l slope <br />2. Replace topsoil above waterline, 6" over 0.7 acres <br />3. Seed and mulch <br />H. Side slope being seeded, 600 ft <br />1. Seed and mulch <br />I. Top of slope <br />I. Seed and mulch <br />4000 CY 0.50 2,000 <br />139 CY 1.25 174 <br />l AC 800.00 800 <br />100,000 CY 2.00 200,000 <br />1852 CY 1.25 2,315 <br />2.3 AC 800.00 1,840 <br />30,000 CY 2.00 60,000 <br />556 CY 1.25 695 <br />0.7 AC 800.00 560 <br />0.7 AC 800.00 560 <br />0.5 AC 800.00 400 <br />