My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
GENERAL53793
DRMS
>
Back File Migration
>
General Documents
>
GENERAL53793
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 8:39:14 PM
Creation date
11/23/2007 8:56:11 PM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
C1982056
IBM Index Class Name
General Documents
Doc Date
3/2/1995
Doc Name
SHAFT CONSTRUCTION PLAN
From
US DEPT OF LABOR MSHA
To
TWENTYMILE COAL CO
Permit Index Doc Type
BLASTING
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
25
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
<br />FOIDEL CREEK MINE <br />^0" ENTRY VENTILATION SHAFT CONSTRUCTION <br />75.220 ROOF CONTROL PLAN ADDENDUM <br />General Description: <br />The "0" Entry shaft will be constructed by raise <br />foot diameter hole and then slashing to 18-foot <br />Following the bore and slashing, the shaft will <br />lined to a finished inside diameter of 16-feet. <br />will be located in the "0" Entry of Crosscut # 1, <br />Mains. <br />Exploration• <br />boring a 5- <br />diameter. <br />be concrete <br />The shaft <br />.n the North <br />The shaft bottom area was developed with a continuous miner as <br />part of the mine development and supported with fully grouted <br />resin 6-foot roof bolts on a 5-foot pattern. Once the raise <br />bore pilot hole penetrates the mine and the raise bore bit is <br />installed, one or two permanent roof bolts may need to be <br />removed. If this is done, timbers will be placed around the <br />circtunference of the raise bore bit to form a new 5-foot <br />pattern of remaining primary bolts and timbers set. Then, the <br />one or two primary roof bolts will be removed. The removal of <br />the timbers will be by remote means from supported roof <br />immediately before iaise boring begins. <br />Shaft Excavation: <br />Upon completion of the 5-foot diameter raise bore hole, the <br />borehole shall be plugged with a metal cage attachment, that <br />provides fall protection but will not close off ventilation, <br />to the work deck. The borehole shall remain plugged at all <br />times except when blasting. Approximately 18-feet diameter <br />will be shot to the center borehole using controlled blasting <br />with permissible powder. All blasting will be done in <br />accordance with requirements of 30 CFR Part 75.1300 or as <br />specified in approval to utilize a non-permissible shot firer <br />unit. The number of holes loaded and shot will be limited to <br />the approved quantity of the blasting machine. After blasting <br />'the borehole, the plug shall be set in place in the borehole <br />via the work deck. The shot material will be mucked into the <br />shaft by air lances with the employees standing on the lower <br />work deck, which has handrails installed around the work deck. <br />1 <br />APPRO`~EO c~r~s & H [~~ip,R 2L.'95 <br />
The URL can be used to link to this page
Your browser does not support the video tag.