Laserfiche WebLink
TR 19 proposed approval decision was issued January 30, 1995 . The <br /> revision proposed that existing Sediment Ponds 1 and 2 be combined <br /> by excavation of a connecting channel , and that Pond 7 and 8 CMP <br /> spillways be replaced by riprapped open channel emergency <br /> spillways. In addition, the revision contained revised designs <br /> incorporating additional capacity in Pond 8 to handle the <br /> possibility of prep plant thickener tank spillage. Ponds 1/2 , 7 <br /> and 8 would all utilize pumping as the primary dewatering <br /> mechanism. As of July 21, 1995, all modifications had been <br /> completed except the final excavation of sediment volume and <br /> certification of the expanded Pond 8, which had been delayed by the <br /> wet spring and high alluvial water table. <br /> TR 20 was deemed complete on January 6, 1995, but no proposed <br /> decision has been issued. Several continuances have been granted. <br /> The TR addressed certain changes in the mine plan including a <br /> modification of the mining schedule to reflect reinitiation of coal <br /> extraction from the North Portal earlier than previously projected <br /> ( in fact North Portal extraction resumed in November, 1994 ) , and an <br /> increase in coal production. <br /> In an adequacy letter dated February 13 , 1995, the Division <br /> requested additional information regarding surface water, ground <br /> water, and subsidence impact evaluation for the North Portal area. <br /> The requested information has not yet been submitted. <br /> TR 21 proposed approval decision was issued with one stipulation on <br /> March 6, 1995. The revision allowed for the construction of a gob <br /> conveyor, screening and crushing plant, an additional truck loadout <br /> bin and associated conveyors within the existing coal handling area <br /> at the Roadside North Mine. <br /> MR 18 proposed approval decision was issued on July 23 , 1993 . The <br /> revision updated Table 2.03 .4 A "OWNERS OF RECORD OF SURFACE AND <br /> SUBSURFACE WITHIN AND CONTIGUOUS TO THE PERMIT AREA" . A cover <br /> letter to the approval decision requested that the operator submit <br /> updated surface and subsurface owner maps (Exhibits 3 and 4) to <br /> correspond to the revised Table. The maps included as Exhibits 3 <br /> and 4 in the permit application volumes on file with the Division <br /> have a certification date of August 31 , 1992 , and were received by <br /> the Division September 3 , 1992, within TR 14 . The requested <br /> replacement maps were apparently not submitted, and there is no <br /> documentation in our files as to why this was not done. <br /> MR 19 proposed approval decision was issued on November 26, 1993 . <br /> The revision updated ownership and control information to reflect <br /> changes in the corporate management structure between Powderhorn <br /> Coal Company and Peabody Holding Company. <br /> MR 20 proposed approval decision was issued May 16, 1994 . The <br /> revision addressed the name change for the mine, from "Roadside and <br /> Cameo Mines" to "Roadside North and South Portals" . <br /> MR 21 proposed approval decision was issued June 24 , 1994 . The <br />