The following is a brief summary of all revisions received by the Division since Permit Renewal <br />04. <br />Technical Revision-59 was submitted on 14 October 2003, called complete on 27 October 2003 <br />and withdrawn by the Operator on 1 December 2003. This revision allowed for the construction <br />and operation of truck and railcar loading systems. These systems were to replace the overland <br />conveyor system currently in use. The revision was withdrawn because it was no longer required <br />for continued operation of the mine. <br />Technical Revision -60 was submitted on 26 August 2004, called complete on 1 September 2004 <br />and approved on 13 October 2004. This revision was submitted in response to Stipulation 53. <br />The revision provided the Division with final reclamation plans for Refuse Pile 2/3/4. <br />Technical Revision -61 was submitted on 5 May 2005, called complete on 16 May 2005 and <br />approved on 21 June 2005. This revision was submitted to allow for the drilling of four <br />additional methane degas wells. The revision replaced Minor Revision-128, which was <br />withdrawn on 3 May 2005. <br />Minor Revision-126 was submitted on 19 April 2004, called complete on 27 Apri12004 and <br />approved on 3 June 2004. This revision allowed for the recontouring of the haul road and the <br />County Road 65 intersection to increase visibility and public safety. <br />Minor Revision -127 was submitted on 19 Apri12004, called complete on 27 Apri12004 and <br />approved on 11 August 2004. This revision allowed for the replacement of approximately 1.2 <br />miles of raw water line from the fresh-water lagoon along Highway 64 to the water tank. <br />Minor Revision -128 was submitted on 6 April 2005, called complete on 15 April 2005 and <br />withdrawn on 3 May 2005. This revision was submitted to allow for the drilling of four <br />additional methane degas wells. The revision was replaced by Technical Revision 61, which was <br />received on 5 May 2005. <br />No Violations were written from the period of the approval of Permit Renewal 04 on 20 October <br />2004 until the present approval of Pennit Revision O5. <br />14 <br />