Laserfiche WebLink
-36- <br />Since the volume of available topsoil is insufficient to cover the entire <br />disposal site to an adequate depth, suitable replacement topsoil will <br />need to be imported. The operator has committed to importing enough <br />suitable topsoil from a local topsoil dealer to reclaim the entire site. <br />The soil will be analyzed prior to placement to be certain of its <br />suitability. Calculations were submitted to show that 86,000 cubic yards <br />of non-toxic fill material and 10,000 cubic yards of soil cover will be <br />needed at the site. The cost of this material is reflected in the bond <br />amount for the operation. <br />Only one concern was noted with the refuse site that has not been <br />resolved. A small "pocket" of colluvial material exl5ts in the bottom of <br />the refuse site valley north-northwest of the pile. This material will <br />be removed in the future as the refuse pile expands. Since the operator <br />did not analyze the full depth of this material, only the first fea feet, <br />the Division is concerned that the material may nut be suitable for use <br />as cover for reclamation of the pile. As a precaution, the Division <br />lmpose5 the following stipulation: <br />Stipulation No. 2 <br />ALL COLLUVIAL MATERIAL AT THE RUFUSE PILE USED AS TOPSOIL OR <br />NON-TOXIC, NON-COMBUSTIBLE DOVER FOR THE REFUSE PILE MUST BE <br />ANALYZED AND APPROVED BY THE DIVISION AS MEETING THE ESTABLISHED <br />CRITERIA FOR SUITABILITY FOR TOPSOIL AND/OR SUBSOIL. <br />The mine loadout facility was constructed in 1980-82. No additional <br />disturbances are anticipated for this site. Nearly all of the soils <br />disturbed by the loadout were agricultural soils and, as such, are an <br />excellent resource for vegetative reclamation. Prior to disturbance, <br />samples were taken at 11 locations to characterize the soils. The <br />following soil types were identified that were disturbed at the loadout: <br />Aquolls, sandy-skeletal, 1-12 percent slopes <br />Atencio-Azeltine complex, 3-6 percent slopes <br />Armells loam, 12-25 percent slopes <br />Armells load, 6-12 percent slopes <br />Armells loam, 1-6 percent slopes <br />Groubutte stony loam, 25-65 percent slopes <br />Unnamed loam, 1-6 percent slopes <br />Almy loam, 1-6 percent slopes <br />Almy loam, 6-12 percent slopes <br />Cushool-Rentsac complex, 15-65 percent slopes <br />Disturbances from construction of the loadout did not involve area-wide <br />excavations or total destruction of the soil profile, as would occur at a <br />strip mine. Except for specific areas under sediment ponds or conveyor <br />and tipple foundations, loadout construction has involved little <br />significant excavation of subsoils. With the exception of Grobutte stony <br />loam, all of the above soils were salvaged and stockpiled to be reapplied <br />during final reclamation. The only disturbance area that was not <br />stripped at the loadout was at the truck dump site. Here, available <br />topsoil d1d not exist due to the steep slope and barren conditions. <br />