Alternatives Considered in Detail <br />Table 2-1 <br />Design Criteria <br />Topic Design Criteria for the Proposed Action <br /> 15. Cross slopes will be maintained on access roads to promote removal Road Use <br /> of water from the road surface. Surface drainage structures shall be Permit(FSM <br /> constructed at appropriate intervals to divert water from roadway 2733.04b and <br /> surface..... Relief ditches at regular intervals to direct drainage off FSM 7730) , <br /> of the road grade and into vegetated areas. WCPH(FSH <br /> 2509.25) <br /> 16. Ditches would be allowed to vegetate or include large rocks or WCPH (FSH <br /> stones to slow the velocity of drainage and allow sediment to settle 2509.25) <br /> out. <br /> 17. Where drainage ditches are installed to direct runoff away from the Project Plan, <br /> road, water bars or hay bale dikes would be installed perpendicular WCPH (FSH <br /> to the flow direction of the ditch to reduce runoff velocity and settle 2509.25) <br /> out sediment on steeper grades. <br /> 18. Road construction plans would identify specific locations of Road Use <br /> drainage features and BMPs for approval by the FS engineer/permit Permit (FSM <br /> administrator prior to construction. 2733.04b and <br /> FSM 7730) , <br /> Forest <br /> Service <br /> Roads Policy <br /> 19. Road design packages will be submitted to the FS for approval prior Forest Plan <br /> to any construction activity. Roads open to the public (Levels 3, 4 <br /> & 5) will require written approval prior to any construction activity. <br /> 20. Project access roads will be gated and closed year-round to the RACR <br /> general public. Personnel with access will be monitored to insure <br /> such access is not abused; i.a, no access during non-working hours <br /> for purposes unrelated to the project such as hunting or off-roading. <br /> 21. All new access roads constructed for the sole use of this project will RACR, 36 <br /> be decommissioned by full obliteration when no longer needed for CFR 228 E, <br /> the project and reclaimed. Road Use <br /> Permit (FSM <br /> 2733.04b and <br /> FSM 7730) <br /> 22. Road work will be performed only upon authorization of the Road Use <br /> District Ranger and comply with the terms of MCC's Road Use Permit (FSM <br /> Permit. Roads will be designed and constructed to provide 2733.04b and <br /> maximum stability and protect the surface resource. Best FSM 7730), <br /> Management Practices will be used in designing the roads and MCC Project <br /> during construction. All roads will be upgraded or constructed to Plan <br /> USFS specified standards for either temporary or classified roads, <br /> as appropriate and approved by the USFS, with a design speed of <br /> 15 miles per hour. <br />Deer Creek Ventilation Shaft and E Seam Methane Drainage Wells FEIS 25 <br />