Phase IVc Summary No. 14 Page 2 043-2170 <br />Ames continued excavation of the Phase IVc Anchor trench on the eastem section of the VLF. Ames <br />excavated approximately 200 feet of anchor trench in preparation of geomembrane installation during <br />this reporting period. <br />Ames continued production of bentonite-amended SLF at the screen plant and pug mill located above <br />the Ames materials yazd. Ames also continued production of Drain Cover Fill (DCF) material at the <br />screen plant by the secondary crusher. <br />Poly-Flex continued deployment of 80-mil single-sided textured LLDPE geomembrane in the Phase <br />IVc OSA. Geomembrane was installed in the Phase PJc OSA on the south facing slope of Raven Hill <br />downwazd to the Phase fVb/IVc tie-in. Poly-Flex deployed 80-mil single-sided textured LLDPE <br />geomembrane over an azea of approximately 298,883 squaze feet in the Phase IVc OSA during this <br />reporting period. Geomembrane panels C-570 through C-657 were deployed, seamed, and tested by <br />Poly-Flex. Destructive fusion seam samples DFc-201 through DFc-234 were mazked and removed. <br />Destructive fusion and extmsion seam peel and shear testing on samples DFc-188 through DFc-213 and <br />DXc-21 were performed and passed per project specification. <br />Ames continued hauling, placement and grading of DCF material into the Phase IVc OSA in the central <br />and eastern sections of the VLF, Raven Hill azea. Ames placed DCF material and High Volume <br />Solution Collection (HVSC) piping per the project plans onto approved geomembrane panels. <br />A map of the azea worked during this reporting period is provided in Attachment C. <br />Field Monitoring and Testing Activities <br />Golder observed construction activities associated with Phase IVc earthworks. All construction <br />materials and soil materials placed were verified as suitable, and construction methods were in <br />accordance with project specifications, <br />Golder observed the excavation and constmction of the LDT in the Phase IVc VLF for trench <br />dimensions (1' wide by 1' deep), slope, and materials used. <br />Golder observed excavation of the Phase IVc anchor trench for proper location, dimension (2' wide by <br />3' deep) and maintenance prior to geomembrane deployment. Anchor trench excavation met or <br />exceeded the requirements of the specification. <br />Golder observed placement, compaction, and moisture conditioning of SLF in the Phase IVc OSA for <br />subgrade preparation, thickness, compaction, moisture-content, and materials used. The Golder CQA <br />Earthworks Monitor performed seventeen nuclear moisture-density tests (SLNc-172 through SLNc- <br />188) and performed seven nucleaz moisture-density retests on SLF that required reworking (SLNc- <br />1676, SLNc-167c, SLNc-171 a, SLNc-171b, SLNc-172a, SLNc-175x, and SLNc-179a). Field test <br />results are presented in Attachment B. <br />Phase Nc l4 AUgutt B-AUg¢[142004 Golder Associates inc. <br />