PERK)DIC STATEMENT FOR PARTIAL PAYMENT N0. 4
<br />PROJECT: Hawks Nest Coal Sib Demolition Reclamation
<br />FOR THE PERIOD 6/16/94 TO 8/2/94 , INCLUSNE
<br />OWNER: State of Colorado, Division of MinuaLs & Geology
<br />Sheet No. 1
<br />CONTRACTOR: Miners Inc.
<br />9137 E. Minual Circle, Suite 160
<br />Englewood, Colorado 80112
<br />STATEMENT OF WORK WORK PERFORMED
<br />Item Description Contract Prev ious This Estimate Total to Date
<br /> Unit $ Unit $ Unit $ Unit $
<br />1.0 Mobilization/Demobilization L.S. $42,248 100% $42,248 0% EO 10096 542,248
<br />2.0 Structural Demoktion & Disposal
<br />. a. Structural Demolition
<br /> Demo Headhouse L.S. $19,250 100% $19,250 0% $0 100% $19,250
<br /> Demo Conveyor L.S. $45,000 100% $45,000 0% $0 100% $45,000
<br /> Drill & Blast Silo #1 L.S. $46,550 10096 $46,550 0% $0 100% $46,550
<br /> Drill & Blast Silo #2 L.S. $46,550 100% $46,550 0% $0 100% $46,550
<br /> Demo Truck Dump & Scale L.S. $14,546 100% $14,546 0% $0 100% $14,546
<br /> Sub-Total $171,896 E171,896 $0 $171,896
<br />b. Disposal/Borrow Area
<br /> ExavateFallingPit L.S. $27,120 100% $27,120 0% $0 100% $27,120
<br /> Demo & Bury Silos L.S. $38,550 10096 $38,550 0% $0 100% $38,550
<br /> Finish Grade Site LS. $4,500 100% $4,500 0% $0 100% $4,500
<br /> Repair Road L.S. $3,500 100% $3,500 0% $0 10096 $3,500
<br /> Sub-Total $73,670 $73,670 $0 573,670
<br />3.0 Additional Dozer Houns 0 $0 0% $0 0% $0 0% $0
<br />4.0 Denver Rio Grande Flagmen 32 Hrs. $1,594 0% - $0 100% $1,594 100% $1,594
<br />5.0 Change Order #1 (Seasonal Conditions) L.S. E3,735 100% $3,735 0% $0 100% $3,735
<br />6.0 Change Order #2 L.S. $3,450 0% $0 100% $3,450 100% $3,450
<br />Total Work kerns $296,593
<br />Material on Hand
<br />u•
<br />Total $296,593
<br />$291,549 $5,044 $296,593
<br />$0 $0 $0
<br />$291,549 $5,044 5296,593