r <br /> <br />Preston Mease <br />Page 4 <br /> <br />further extended 15 days to accommodated machine time necessary to topsoil Chen's <br />Hill and the final date set at July 5, 1994. Actual completion was on July 12, 1994 <br />resulting in 7 days of liquidated damages or $2100.00. <br />All items on the punch list have been completed to the Division of Minerals and <br />Geology's satisfaction except proper riprap placement in Chen's Hill Ditch. The <br />amount of rock on the bottom of the ditch is unacceptable as observed by the <br />project manager and Coal Program personnel. This will need to be corrected before <br />release of retainage is made. <br />If you have any questions about any of the above statements please call at (303) 866-3567. <br />Sincerely, <br />m:\imp\yjb\john.l~r <br />