Laserfiche WebLink
Reporting Period September 2, 1997 -September 7, 1997 <br />4 <br />Shaft Site #3: As of 9/7, approximately eleven benches have been completed using top <br />down construction methods. All benches except the top two have been excavated into hard <br />sandstone rock. Slopes are dry and stable. Further field modifications, consisting of <br />reorientation of the open channel drainage paths for stormwater control, have been made as <br />the site has been cleared and graded in order to better match the natural topography. Ditch <br />and culvert lengths will be less than previously anticipated. As-built drawings will be <br />forwarded to CDMG staff once the site is completed. <br />If you have any questions or concerns, please feel free to contact me at (970) 929-2207. <br />Sincerely, <br />~' <br />Eric W. Mende, P.E. <br />E-Seam Project Civil Engineer <br />EWM/mer <br />Attachment <br />xc: Christine Johnston -MCC w/o Attachment <br />Phil Schmidt -MCC w/o Attachment <br />Steve Westbay -Gunnison County w/o Attachment <br />File w/Attachment <br />