<br />AC[achmen[ 3.4. Regrade Rate ($/hr). <br />Regrade hours = 26,554.9 (original) + g0.0 (87 Rev) = 26,474.9 <br />Dozer shifts = (26,474.9 hrs)/(6.25 hrs/shifts) = 4,236.0 <br />Dozer months = (4,236.0 shiEts)(84 shifts/month) = 50.4 <br />Lease costl = ($36,215/mo)(50.4 mo) _ $1,825,236.00 <br />MOB/DECf082 = ($1,827.00)(2)(1.05)306 dozers) = 526,648.76 <br />Average lease rate = (51,825,236.00 + S26,648.76) 569.95/hr <br />26,474.9 <br />Operating cost (Blue Book) _ $43.05 x 1.03 (area factor) _ $44.34/hr <br />Labor3 (International Agreement-Operating Eng) <br />($13.93/hr)(66)+1.5(13.93/hr)(18) 8 Labor hrs <br />84 x 1.0692 x 6.25 egpt hrs- 521.11/hr <br />Tocal Regrade Rate <br />= 5135.40/hr <br />1. Based on Wagner quo [e for D9L, minimum 6-munch Lease. <br />2. 51,827 is quoted one-way race of 11/82; (1.05)4 used to escalate [o <br />1/87. <br />3. $13.93/hr based on International Agreement covering Colorado Highway, Heavy <br />and Engineering Work Between International Union of Operating Engineers and <br />the Independent Contractors Committee - current rate. <br />66 straight-time shifts and 18 OT shifts per month. <br />6.92~o Workmen's Compensation. <br />JMhf/aec 1/87 <br />