Phase IVb Weekly Summary No. 17 Page 3 003-2203 <br />Geomembrane panels M-637 through M-654 were deployed, seamed; and pressure tested by Poly-Flex. <br />Destructive fusion seam samples DF-172 through DF-174 and extrusion seam samples DX-33 were <br />marked and removed. Destructive fusion and extrusion seam peel and shear tests of these samples were <br />not performed during this reporting period. <br />A map of the area worked is provided in Attachment C. <br />Phase IVc <br />Ames continued limited cut and placed the material in temporary stockpiles within the limits of the <br />Phase IVc area. <br />Field Monitoring and Testing Activities <br />Golder observed construction activities associated with Phase N earthworks, All construction <br />materials and soil materials placed were verified as suitable, and construction methods were in <br />accordance with project specifications. Removal of oversized or deleterious material from all fill <br />areas was observed. Golder observed SF placement in Phase IV for materials, lift thickness, <br />moisture content, and compactive effort. <br />Golder observed re-compaction of LVSCF in the Phase IVb PSSA sump after rainfall flooded the <br />area. The HVSCS riser foundations were compacted and re-graded. Golder CQA monitors <br />performed four nucleaz moisture-density tests (LVSCNb-Ola through LVSCNb-04a) on.LV$CF re- <br />compacted within the Phase IVb PSSA sump. The tests performed met the requirements of the <br />specifications and the nuclear moisture-density results summary is presented in Attachment B. <br />Golder visually observed the placement and grading of LVSCF in the Phase IVb PSSA area. Golder <br />CQA monitors (one monitor per dozer when dozers are greater than 50 ft apart) observed LVSCF <br />placement and verified minimum thickness of 3 feet. <br />Golder visually observed the placement of DCF in the Phase IVb PSSA area. Golder CQA monitors <br />(one monitor per dozer when dozers are greater than 50 ft apart) observed DCF placement and <br />verified minimum thickness oft feet. <br />Golder observed anchor trench excavation in the Phase IVb PSSA and OSA for proper location and <br />dimension (2' wide by 3' deep). Anchor trench excavation met or exceeded the requirements of the <br />specifications. Golder observed anchor trench bac_kfill in the Phase IVb PSSA for lift thickness and <br />compaction. <br />Golder observed construction of the Primary Underdrain in Phase IVb for trench dimension (5' wide <br />by 3' deep), slope (minimum 1%), materials, and geotextile overlap. Primary Underdrain <br />construction met or exceeded the requirements of the specifications. <br />Golder observed and monitored placement of Bedding Fill (BF) in the Phase IVb PSSA for proper <br />location and thickness (1' deep). Golder monitored compactive effort and fmish grading to verify <br />conditions met specification. <br />Phaze Rb ^MaylLMayp, 200'a doc Golder Associates Inc. <br />