Laserfiche WebLink
7. Cover outslope of bench with overburden and available topsoil <br />• to a depth of four feeC (approximately 16,000 cubic yards). Topsail <br />presently stockpiled on the mine site will be used because the <br />restabilized bench will be in its final reclamation configuration. <br />8. Revegetation according to plan approved in the permit for <br />final reclamation <br />The time table for this project is expected to be as follows: <br />Late August, 1984 - Rocky Mountain Geotechnical, Inc. reporC <br />to be submitted to the Division. <br />September, 1984 - Receive approval from the Division, begin <br />stabilization of the bench, and begin installation of drainage control. <br />October and November, 1984 - Fill and cover bench as fat as <br />possible until winter weather stops work. Revegetation will start <br />if progress on the project allows. <br />• Spring and through August, 1985 - Finish fill and cover. <br />Fall, 1985 - Finish revegetation. <br />• -3- <br />