EXHIBIT E <br />RECLAMATION PLAN <br />As stated in Phase 1 Mining Plan, when mining approaches 1800' easterly, reclamation <br />will start on west permit boundary following at the same rate as mining is moving easterly. <br />Overburden will be used to cover pit areas and bring north slopes to less than 3:1. Six to twelve <br />inches (6-12") of topsoil will be spread over these areas. Seeding, mulching and fertilizing will <br />take place on pit and stockpile areas. As Phase 2 is completed, the entire Phase 1 area will be <br />sloped, overburden and topsoil spread, seeded, mulched and fertilized. <br />When Phase 3 is completed, all of Phase 2 & 3 will be reclaimed in the same manner. <br />The affected areas will be seeded according to grass mixes recommended by the Rio Blanco <br />County Soil Conservation Service to bring affected areas back to rangeland as it was in pre- <br />mining times. A weed control program will be developed with the Rio Blanco County Weed <br />Control District with annual inspections to be made. <br />~~ ~ y <br />