~•SEP 05 '% 01~52PM PEABODY WSTN SENECA MINE P.4 <br />Ms, Erica Crosby <br />September 4, 1996 <br />Page 3 <br />Engineering Depts. We were hoping that Mr. Draper would allow us to <br />place. the excavated material from RCR 27A along the shoulder of RCR <br />27 to minimize the diaturbance on the Hallenbeck property. we <br />Further explained that the revision submittal showed the ^worst- <br />case" diaturbance on the Hallenbeck property, since it included the <br />detour road for traffic while the dragline crossed RCA 17. This <br />deigtir would h~sve caused approximately 4 acres of diaturbance, <br />-~.noluding tale removal and reconstructing of a stockpond on the <br />Hallenbeck property. Neither you nor Larry asked about the work <br />associated with the widening of RCR 27A and why it was sot <br />permitted by Seneca. <br />Mr. Draper did come out for our meeting in the morning on the 22nd. <br />since we told him that RCR 27 would' need to be closed for <br />approximately two hours to cross it with the dragline, he stated <br />the: instead of doing all of the adflitional disturbance associated <br />Grid the extra detour road that the county will close the road the <br />morziing of the crossing. He thought it was a good idea to use the <br />excavated material from RCR 27A and place it adjacent to RCR 27 <br />witYein our existing easement on this road, minimizing the <br />disturbance. Mr. Draper said that he had no problems with the <br />deadhead plans and informed us we could start the next day with the <br />wide.nirq of RCR 27A. <br />On Friday Auyust 23, I called Larry and left a voice message that <br />we had received approval from Routt county to qo ahead with <br />widening RCR 37A and to place the fill alongside RCR 27, within the <br />mxistinq county road easement. When the Xoast permit was approved <br />in August 133°, the county requested that we add a turn lane in <br />both. directions at the intersection of RCR 27 and Yoast Haul Road <br />"~°' for safety reasons. These two lanes were not included in the <br />'!oast permit area, yet they were discussed with the Division, since <br />they were constructed at the request of the county. We felt the <br />{ii' along P,CR a7, associated with the widening of RCR 27A, was a <br />similar c~.rcumstance since the county approved it even though TR-03 <br />had not yet been approved. Work started that morning. <br />Un Monday Augus+;, 26, we had a phone Conversation on several issues <br />and I mentioned to ycu that we started the work on widening RCR <br />27A. Within the hour, Larry called me back asking several questions <br />abet±t this work. i asked him if the Division had a problem with <br />what we were doing, I would be happy to atop the work until we were <br />giver. the qo ahead by the Division. Larry said that we could <br />continue with the widening. Seneca received the oversize permit to <br />•walk the dragline on RCR 27A and RCR 27 on August 28, a Copy was <br />faxe3 to zrou on August 29. We received the Administrative Permit <br />z%ott+ the Routt County Regional 8lanning Commission, for this <br />dead:`l~d project on Auquat 30. <br />