RECLAMATION PLAN <br />1. Lake Area Reclamation <br />EXHIBIT E <br />The reclamation of the lake is relatively simple since the mining itself is excavating the lake to its final <br />grade of 3H:1.OV. The armoring & revegetation of the bank and the construction of the jetty will have <br />been completed prior to lake excavation, therefore these items are not part of the reclamation plan. <br />It is planned that the small portion of land between the southwest permit boundary and the west edge of <br />the lake will be restored to irrigation use. This area is approximately 0.80 acres. Prior to replacing top- <br />soil for this area, regrading for irrigation will take place and the area will be deep-ripped to at least 24 <br />inches to relieve any compaction in the subsoil. The inside part of the lake itself will be retopsoiled <br />above the expected waterline of 6656' elevation. Topsoil for both of these areas will be obtained from <br />the stockpile located immediately east of the lake. The lake will be seeded along the inside 3H:1V <br />slopes and the top of dam. Wetland plants will also be seeded along the expected waterline. The lake <br />and upper slopes above the waterline will be used for wildlife habitat. <br />Once the irrigation area has been returned to its intended use, the sediment sump and outlet ditch at the <br />south end of the property will be reclaimed. Material to backfill this area will also come from the adja- <br />cent topsoil stockpile. See table below for calculations: <br />Area Restored Acreage Topsoil thick- <br />Hess in ft Volume of soil <br />needed in cy Land Use <br />Field east of lake 0.80 1.4 1806 Irrigation <br />Inside of lake 1.42 0.5 1145 Wildlife Habitat <br />Sediment Sump <br />and Ditch 0.16 1.2 309 Irrigation <br />Water surface 3.28 0 0 Wildlife Habitat <br />Totals 5.66 3260 <br />Thomas Pit 2/02 25 <br />